Nochmal der aktuelle Shafter-Status vom Januar und die Planungen
für Februar in Erinnerung gerufen:
Shafter Mine Construction Milestones completed in Q4,
2011
The Company commenced construction of the Shafter Mine in January,
2011 with an anticipated completion date of May 2012. Significant
Q4, 2011milestones on the Shafter Mine include:
- Ramp is now 1,134 feet underground, and will reach the first
resource block in January, 2012.
- Ball Mill completed, 6 Leach Tanks along with Pregnant and Barren
Tanks, Mine Office completed in December, as planned.
- The Merrill Crowe Equipment delivered and 70% installed.
- Initiated refurbishing #46 shaft for ventilation.
- Jaw crusher and cone crusher have been installed, ready for
commission in January, Filter Press Structure and Filter Presses to
be installed in January.
- Assay Lab construction begins in January.
- Underground Production Equipment continues to arrive as
scheduled.
- 95% of concrete work has been completed, finalized by
February.
- Final projects to complete: Cyanide mixing plant, warehouse
building, potable water system
Bald kann die Produkton also losgehen! Ich freu mich drauf!