DGAP-Adhoc
BDI - BioEnergy International AG: difficult market environment and project delays depress earnings
BDI - BioEnergy International AG / Key word(s): Profit Warning
25.07.2014 08:18
Dissemination of an Ad hoc announcement according to § 15 WpHG, transmitted
by DGAP - a company of EQS Group AG.
The issuer is solely responsible for the content of this announcement.
---------------------------------------------------------------------------
BDI - BioEnergy International AG: difficult market environment and project
delays depress earnings
(Grambach, 25.07.2014) On the basis of provisional calculations, BDI -
BioEnergy International AG ("BDI"), the leading technology supplier and
specialised plant manufacturer in the field from waste to value, generated
sales of EUR 8.6 million (previous year: EUR 16.6 million) and an operating
result (EBIT) of EUR -2.4 million (previous year: EUR 0.7 million) in the
first half of 2014. In the current fiscal year the economic development is
influenced by the on-going difficult market environment in the field of
renewable energies as well as by project delays in both the BioDiesel and
the BioGas operations.
On the basis of the preliminary figures for the first half of the year and
in view of probable project delays, particularly of a plant in Croatia, the
company anticipates lower sales and an operating loss in the fiscal year
2014. Due to the company's solid financial position, however, the loss can
be partly compensated by corresponding positive financial earnings. The
total orders on hand amount to about EUR 70 million and guarantee the
utilisation of the capacities as well as a positive development in earnings
in the subsequent years.
BDI is working intensively on the strategic expansion of the business
operations by broadening the core skills in the green tech field. Due to
the progress made in research and development projects but also due to the
potential acquisition of complementary environmental technologies BDI is
confident that it will be able to achieve sustainable success in the medium
term.
---------------------------------------------------------------------------
Information and Explaination of the Issuer to this News:
About BDI - BioEnergy International AG
BDI - BioEnergy International AG is market and technology leader in the
construction of customised BioDiesel plants using the Multi-Feedstock
Technology the company has developed itself, which can manufacture
BioDiesel from different raw materials, such as Vegetable Oils, Used
Cooking Oils and Animal Fats.
BDI has specialised in the development of technologies that make optimum
use of resources in the industrial processing of by- and waste products
ever since it was established in 1996 and owns an extensive patent
portfolio that has resulted from its in-house research and development
activities. As a leading constructor of special plants, BDI also supplies
efficient plant concepts in the from waste to value field that are designed
to produce BioGas from industrial and municipal waste. The range of
services includes public authority, basic and detailed engineering,
installation and start-up as well as after-sales support.
BDI - BioEnergy International AG and the companies it consolidates
currently have about 110 employees. The shares of BDI - BioEnergy
International AG (ISIN AT0000A02177) are listed in the General
Standard/Regulated Market at Frankfurt Stock Exchange.
Contact for further information:
Edgar Ahn, PhD
Member of the Management Board, CSO
BDI - BioEnergy International AG
Parkring 18
A-8074 Grambach/Graz, Austria
Tel: +43 / 316 / 4009 - 100
Fax: +43 / 316 / 4009 - 110
www.bdi-bioenergy.com
bdi@bdi-bioenergy.com
25.07.2014 DGAP's Distribution Services include Regulatory Announcements,
Financial/Corporate News and Press Releases.
Media archive at www.dgap-medientreff.de and www.dgap.de
---------------------------------------------------------------------------
Language: English
Company: BDI - BioEnergy International AG
Parkring 18
A-8074 Grambach/Graz
Austria
Phone: +43 - 316 - 4009-100
Fax: +43 - 316 - 4009-110
E-mail: bdi@bdi-bioenergy.com
Internet: www.bdi-bioenergy.com
ISIN: AT0000A02177
WKN: A0LAXT
Listed: Regulierter Markt in Frankfurt (General Standard);
Freiverkehr in Berlin, Düsseldorf, München, Stuttgart
End of Announcement DGAP News-Service
---------------------------------------------------------------------------
delays depress earnings
(Grambach, 25.07.2014) On the basis of provisional calculations, BDI -
BioEnergy International AG ("BDI"), the leading technology supplier and
specialised plant manufacturer in the field from waste to value, generated
sales of EUR 8.6 million (previous year: EUR 16.6 million) and an operating
result (EBIT) of EUR -2.4 million (previous year: EUR 0.7 million) in the
first half of 2014. In the current fiscal year the economic development is
influenced by the on-going difficult market environment in the field of
renewable energies as well as by project delays in both the BioDiesel and
the BioGas operations.
On the basis of the preliminary figures for the first half of the year and
in view of probable project delays, particularly of a plant in Croatia, the
company anticipates lower sales and an operating loss in the fiscal year
2014. Due to the company's solid financial position, however, the loss can
be partly compensated by corresponding positive financial earnings. The
total orders on hand amount to about EUR 70 million and guarantee the
utilisation of the capacities as well as a positive development in earnings
in the subsequent years.
BDI is working intensively on the strategic expansion of the business
operations by broadening the core skills in the green tech field. Due to
the progress made in research and development projects but also due to the
potential acquisition of complementary environmental technologies BDI is
confident that it will be able to achieve sustainable success in the medium
term.
---------------------------------------------------------------------------
Information and Explaination of the Issuer to this News:
About BDI - BioEnergy International AG
BDI - BioEnergy International AG is market and technology leader in the
construction of customised BioDiesel plants using the Multi-Feedstock
Technology the company has developed itself, which can manufacture
BioDiesel from different raw materials, such as Vegetable Oils, Used
Cooking Oils and Animal Fats.
BDI has specialised in the development of technologies that make optimum
use of resources in the industrial processing of by- and waste products
ever since it was established in 1996 and owns an extensive patent
portfolio that has resulted from its in-house research and development
activities. As a leading constructor of special plants, BDI also supplies
efficient plant concepts in the from waste to value field that are designed
to produce BioGas from industrial and municipal waste. The range of
services includes public authority, basic and detailed engineering,
installation and start-up as well as after-sales support.
BDI - BioEnergy International AG and the companies it consolidates
currently have about 110 employees. The shares of BDI - BioEnergy
International AG (ISIN AT0000A02177) are listed in the General
Standard/Regulated Market at Frankfurt Stock Exchange.
Contact for further information:
Edgar Ahn, PhD
Member of the Management Board, CSO
BDI - BioEnergy International AG
Parkring 18
A-8074 Grambach/Graz, Austria
Tel: +43 / 316 / 4009 - 100
Fax: +43 / 316 / 4009 - 110
www.bdi-bioenergy.com
bdi@bdi-bioenergy.com
25.07.2014 DGAP's Distribution Services include Regulatory Announcements,
Financial/Corporate News and Press Releases.
Media archive at www.dgap-medientreff.de and www.dgap.de
---------------------------------------------------------------------------
Language: English
Company: BDI - BioEnergy International AG
Parkring 18
A-8074 Grambach/Graz
Austria
Phone: +43 - 316 - 4009-100
Fax: +43 - 316 - 4009-110
E-mail: bdi@bdi-bioenergy.com
Internet: www.bdi-bioenergy.com
ISIN: AT0000A02177
WKN: A0LAXT
Listed: Regulierter Markt in Frankfurt (General Standard);
Freiverkehr in Berlin, Düsseldorf, München, Stuttgart
End of Announcement DGAP News-Service
---------------------------------------------------------------------------
Aktuelle Themen
Weitere Artikel des Autors
1 im Artikel enthaltener WertIm Artikel enthaltene Werte