     367  0 Kommentare Copper North Progress at Carmacks Project, Yukon

    VANCOUVER, BRITISH COLUMBIA--(Marketwired - Sept. 2, 2014) - Copper North Mining Corp. ("Copper North" or the "Company") (TSX VENTURE:COL) is pleased to update its progress on the re-engineering of the Carmacks Project in north central Yukon. Several initiatives are now underway for improving the operations plan and reducing the capital cost of development of the Carmacks Project.

    Initial investigations focused on the recovery of gold and silver alongside the leaching of copper; resulting in an increase in mine revenues, a minor increase in capital expenditure, and a reduction of the cost to produce copper, after deduction of gold and silver credits.

    With the completion of the Preliminary Economic Assessment ("PEA"), efforts are now focused on evaluating alternative processing plans and opportunities for the reduction of capital expense for the mine facilities (see May 30, 2014 news release).

    The addition of a gold and silver leach, alongside the copper leach, warranted a review of the optimal leach plan to maximize both copper and precious metal recovery. A mini-study comparing vat leaching of copper to heap leaching of copper utilizing an on/off leach pad indicated that the capital costs are similar; however, there may be significant operational benefits from using vat leaching.

    Vat Leach Alternative

    The vat leach process of submerging the crushed ore in weak sulphuric acid, removes much of the operating complexity of leach pads and simplifies environmental management of an on/off leach pad, especially under winter weather conditions. Secondly, it provides for preparation of optimal conditions for cyanide leaching of the spent copper leach material for high recovery of gold and silver. The rapid leach time expected in vat leaching (3 to 5 weeks) provides for an early start for cyanidation of recovery of gold and silver.

    A bulk sample is being prepared to undertake the vat leach test work and prepare the leached materials for the cyanidation test work. This is the key additional information necessary to finalize the new processing and development plan and commence the preparation of a new feasibility study and environmental assessment report for re-entry to the permitting process.

    Benchmarking and Capital Expenditure Reduction Opportunities

    Comparison of capital costs for similar projects have indicated that there are opportunities for the reduction of capital expenditures; particularly, for equipment used in the processing area. Copper North has met with three well accredited engineering institutes in China to discuss the provision of detailed engineering and procurement of certain equipment for the processing or Carmacks ores.

    Seite 1 von 3



    Verfasst von Marketwired
    Copper North Progress at Carmacks Project, Yukon VANCOUVER, BRITISH COLUMBIA--(Marketwired - Sept. 2, 2014) - Copper North Mining Corp. ("Copper North" or the "Company") (TSX VENTURE:COL) is pleased to update its progress on the re-engineering of the Carmacks Project in north central Yukon. …