Fenster schließen  |  Fenster drucken

Press Release #07-15

Western Prospector Group Ltd. ("Western Prospector") and its Mongolian
subsidiary Emeelt Mines LLC ("Emeelt") today announced the completion
of a Preliminary Economic Assessment Study of a production plan for its
100% owned Gurvanbulag deposit in Mongolia.

The Preliminary Economic Assessment report (the "Micon Report") was
completed by mineral industry consultants, Micon International Limited
("Micon") of Toronto, Ontario, who based their report on: an
independent resource estimate (compliant with NI 43-101) prepared by
SRK Consulting (Canada) Inc. ("SRK"), metallurgical testwork conducted
by SGS Lakefield Research Limited under the direction of Melis
Engineering Ltd., preliminary processing flowsheet developed by Melis
Engineering Ltd., and preliminary site selection of tailings storage
facilities by Golder Associates Ltd. ("Golder")

The Micon Report outlines the preliminary economics of developing an
underground mine and surface processing facility with an average
throughput of 1,500 tonnes per day to produce annually approximately
2.0 million pounds U3O8 as yellowcake over a project life of 10 years
with average operating costs of US$86.50 per tonne milled or
US$24/pound U3O8. The Micon Report states that, based on assumptions
and parameters (summarized below), the Gurvanbulag deposit cash flow
yields an after tax IRR of 35% and NPV of US$241 million, using a
discount rate of 10% per year. Micon has recommended continued
exploration at Gurvanbulag to identify further resources,
infrastructure establishment, securing construction and development
permits, on-going environmental baseline studies, and completion of a
Full Feasibility Study.

The Preliminary Economic Assessment was directed to the classified
resource portion of the central or core area of the Gurvanbulag
deposit. Additional resource potential, as indicated by unclassified
historic Russian C2 resources, will soon be drill-tested around the
periphery of the central Gurvanbulag deposit. Western Prospector
reported on May 8, 2007 that SRK outlined an indicated resource of 13.6
million pounds U3O8 and an additional inferred resource of 8.6 million
pounds U3O8 utilizing a 0.07% U3O8 cut-off based on a long-term price
of $47 per pound U3O8 and an internal estimate of potential operating
costs for underground mining. The SRK classified resources are
tabulated below.

http://www.westernprospector.com/i/misc/table01.gif

The configuration of the mineralized zones requires the use of flexible
and selective mining methods, which can accommodate variability in
width and dip of mineralization. Stopes will initially be accessed from
existing development on the 260 m level. As mining proceeds, subsequent
intermediate access levels will be developed from the internal ramp
upward towards the 80 m level. Later in the mine life, the lower mining
horizons will be accessed from the 440 m haulage level and intermediate
access levels will be developed from the internal ramp, up to the 260 m
level.

Given the mineralization geometry and presently known resources a mine
production rate of 1,500 t/d was selected resulting in a mine life of
approximately 10 years.

Metallurgical testwork for the Gurvanbulag project was carried out on
samples of drill core received in June, 2006. The testwork program
included grindability, leaching, liquid/solid separation, solvent
extraction, precipitation and tailings preparation.

Golder was retained by Western Prospector to provide a preliminary
assessment of potential sites for the location of a tailings management
facility (TMF) at Gurvanbulag. Western Prospector has provisionally
selected a preferred location for the tailings management facility.
This is based, principally, on the distance from the Main shaft (1.6
km) and in order for the tailings management facility and the mill to
be located within the same watershed. It has been assumed that
approximately 50% of the total tailings will be returned to the
underground mine as paste backfill.

It is proposed that a new road will be constructed to connect the
Gurvanbulag site with the town of Choibalsan. The road, approximately
117 km long, is anticipated to follow the route of the power line that
is currently under construction. The feasibility study and route design
have been completed by the civil engineering firm, Avarga Zam Co. Ltd.
of Mongolia.

Permanent power supply will be provided by a new 110-kV line from the
power station operated by Dornod Energy System LLC (DES) at Choibalsan.
The power line is now being constructed under a joint venture agreement
executed by Emeelt and XinXin Mining. XinXin, is developing its Ulaan
base metals mine 7 km to the east of the Gurvanbulag mine site. In
addition, power could be supplied to the soum communities of Bayandun,
Dashbalbar and Gurvanzagal, none of which presently is connected to the
electrical grid.

Accommodation is provided in a new facility that has been constructed
5.5 km south of the mine site. The facilities comprise a 200-person
capacity camp that was constructed in mid-2006 by Geomandal Star LLC.

ECONOMIC EVALUATION

Based on the mineral resources estimated by SRK, Micon has developed a
plan to mine and process an average of 1,500 t/d of mineralized
material that results in mining all of the presently estimated 5.4 Mt
of resources over a project life of about 10 years. Mining by inclined
room and pillar with backfill methods is projected to provide a mining
recovery of 93% with 5% dilution at zero grade. The proposed on-site
processing plant was based on metallurgical test results that yielded
95% recovery utilizing an acid leach system. Pre-production capital
cost was estimated at US$229 million. The cumulative operating
after-tax net cash flow, assuming a royalty payable of 5%, a tax rate
of 25% and a uranium price of US$84/lb U3O8, was US$643 million.
Discounted at 10% per year, the net present value was US$241.5 million.
The project is sensitive to uranium prices in that a 10% variance in
uranium price is expected to yield a 5% variance in the IRR (see
cautionary note).

The estimates of capital and operating costs are combined in the
discounted cash flow evaluation for which a summary of the base case is
shown in the table below. Capital and operating costs have been
estimated to a level of detail appropriate for a preliminary economic
assessment, in this case to an overall level of +/-25%. The economic
evaluation is treated on a full project basis, i.e., assuming 100%
equity financing and, for the base case, a uranium price of $185/kg
U3O8 (equivalent to $84/lb U3O8) has been assumed.

http://www.westernprospector.com/i/misc/table02.gif

Among the factors assumed in the development of the cash flow model
are:

- Mining recovery 93%, dilution 5% at zero grade.
- Production rate of 1,500 t/d, operating 365 days per year.
- Plant recovery 94.9%.
- Sunk costs of $81.4 M have been included in the capital write off.
- A royalty of 5% of revenue has been assumed.
- A tax rate of 25% of taxable income has been assumed.
- Analyses are in constant US dollars of mid-2007 value.

Based on these assumptions and analyses, the project cash flow yields
an IRR of 35% after tax. The NPV at a discount rate of 10%/y is $241 M.

The project cash flow is sensitive to uranium price, operating costs
and capital costs. As may be expected, the price of uranium is the most
sensitive item, followed in turn by capital and then operating costs.
The results on IRR and net present value of varying the grade of
uranium by 10% and 25% are the same as for the price of uranium.

http://www.westernprospector.com/i/misc/table03.gif

The results of the base case discounted cash flow analysis of the
Gurvanbulag project indicate that, at an IRR of 35% after tax, the
project is robust. In common with virtually all mining developments,
the project cash flow is most sensitive to revenue, in this case, to
the price of uranium and grade of the deposit. The result of reducing
either the price of uranium or the mined grade by 25% is an IRR of 22%
which also supports the robustness of the project. The estimated grade
will be further evaluated through the planned exploration program.

CONCLUSIONS AND RECOMMENDATIONS

Micon recommends Western Prospector/Emeelt proceed to initiate work on
a full feasibility study for the Gurvanbulag project along with
recommendations that include; continued exploration at Gurvanbulag and
in the surrounding area with the objective of increasing the identified
mineral resources and, potentially, increasing the life of a mining and
processing operation at Gurvanbulag, and compilation into an updated
estimate of mineral resources based on the results of exploration
through the second half of 2006 and 2007. It should be noted that the
results of full feasibility study of the Gurvanbulag project are likely
to differ from the results of this preliminary economic assessment.

Accordingly, Western Prospector is now focusing on adding additional
resources to the classified resource base at Gurvanbulag through a
continuing program of underground sampling, gamma logging of
underground drill holes and surface drilling, following which an
additional resource estimation will be done in preparation for
commencement of a full feasibility study. The Gurvanbulag development
schedule is estimated at 30 months from the completion of full
feasibility study to initiation of commercial production in late 2010.

Qualified Persons: Jane Spooner, M.Sc., P.Geo, of Micon International
Limited, and Mani Verma, P.Eng., and Malcolm Buck, P.Eng., both
Associate Mining Engineers with Micon International Limited., Bruce
Fielder, P.Eng., Principal Process Engineer of Melis Engineering Ltd.,
Marek Nowak, MA.Sc., P.Eng., Principal Geostatistician with SRK
Consulting, and Gerald Harper, Ph.D., P.Geo., Vice-President
Exploration and Wayne Roberts, P.Geo., Senior Vice-President of Western
Prospector Group Ltd., are the qualified persons (as defined under NI
43-101) on the project and have reviewed the technical information
presented in this release.

CONFERENCE CALL

A conference call will be held, Tuesday, October 16, at 1:00 pm
Eastern, 10:00 a.m. Pacific. To participate in the conference call,
please dial 416-644-3417 or 800-731-5319. A replay of this conference
call will be available for one week starting Tuesday, October 16, at
3:00 pm Eastern or 12:00 pm Pacific. To listen to the replay, please
dial 416 640 1917 or 877 289 8525, pass code 21250293#.

"Eric Bohren"

Eric Bohren

President and CEO
 
aus der Diskussion: Western Prospector: Gold, Uran und vieles mehr!
Autor (Datum des Eintrages): Ikar  (17.10.07 21:02:57)
Beitrag: 25 von 34 (ID:32056609)
Alle Angaben ohne Gewähr © wallstreetONLINE