Nun steht auch ein provisorischer Terminplan:

siehe :

1.6 EXPLORATION AND DEVELOPMENT PLAN
Scotgold plans to invest approximately GB£1 million into exploration for the calendar year 2010. Work
commencing in Q1 2010 will focus on the Cononish property, where 1,000 m of NQ diamond drilling
will in-fill sections of the current resource. Additional drilling aims to extend the current resource area.
Scotgold expects this phase of work will be completed by end Q2 2010.
A planning application for mine development and operation was lodged with the planning authority on
25th January 2010, with a permit decision expected in early June 2010. Once permission is granted, it
will take approximately three months to commence underground and site works (commencement in
September 2010). The period to achieve construction and production is expected to be around 12
months, giving September 2011 for steady state production. Tailings Management Facility (“TMF”)
construction is scheduled to commence around August 2010, with commissioning in September 2011.
Plant construction time is estimated at seven months, plus transport and commissioning - giving a key
100206_FINAL_L174_SCOTGOL_AIM CPR_G_Au.doc Page 9 of 51
decision point at October 2010 for the order to be placed. Full plant operation is planned for September
2011.


Die Details dazu unter Pkt. 1.6 des Berichts von SNOWDEN

http://www.scotgoldresources.com/assets/pdf/asx/AIM_Admissio…

Picker56
 
aus der Diskussion: SCOTGOLD RES. eine Mine mit Wachstumspotential?
Autor (Datum des Eintrages): Picker56  (11.02.10 19:31:40)
Beitrag: 36 von 123 (ID:38928971)
Alle Angaben ohne Gewähr © wallstreetONLINE