Western Areas Ltd (“Western Areas” or the “Company”) is pleased to announce that the early capital works at the Odysseus Project (ASX release 22 October 2018) have been completed as planned and to budget, with several key recent milestones achieved:

• Decline rehabilitation completed down to the 10,000m RL pump station (500m Below Surface), with pump station mechanical and electrical designs complete.

• Dismantling of purchased shaft headgear and winder commenced and expedited in South Africa. Delivery to Perth expected in third quarter of FY2020, to support hoisting shaft operations.

• All required tenders and contracts for ongoing works awarded or substantially complete.

• Successful recruitment of experienced Project Manager and Construction Manager with extensive shaft construction experience.

...

 