Heute eine neue Aussage auf der HP/Investors/Q & A:

"It has always been about 24 months to full production and is comprised of many subsidiary schedules, each of which has its own critical path and its own flexibilities. Mining only needs a quarter of the 24 months, bulk earthworks a bit more, plant assembly about half of it, community about a quarter of it and so on. The development team and contractors have done this many times."

Sagt Alles und nix aus...

VG
WH67
 
aus der Diskussion: KEFI Gold and Copper - First Mover in ETH und SAU
Autor (Datum des Eintrages): Walhai67  (28.11.19 12:55:39)