Outotec's Financial Statements Review January-December 2018 -- ilmenite smelter project
https://www.outotec.com/company/media/news/2019/outotecs-fin…

=>


...
Financial guidance for 2019

Based on the current market outlook, we expect our sales to increase, and our aEBIT* to increase significantly from the 2018 aEBIT (EUR 63.8 million) without the provision for the ilmenite smelter project.

*Excluding restructuring- and acquisition-related items, as well as PPA amortizations...



=> Schadensprovision in SA ("provision for the ilmenite smelter project"):

Outotec has made a EUR 110 million provision for possible costs relating to the ilmenite smelter project in Saudi Arabia (Stock Exchange Releases on May 31, 2012; October 26, 2018; October 30, 2018 and February 8, 2019).

The currently estimated provision is based on progress made with the analysis of the furnace. The provision is booked in Outotec's fourth quarter 2018 result. The outcome of the analysis, together with other factors such as Outotec's contractual position, will determine the eventual liability and financial impact of this incident for Outotec.
Antwort auf Beitrag Nr.: 59.824.404 von faultcode am 08.02.19 13:26:56aus den "FINANCIAL STATEMENTS AND REPORT BY THE BOARD OF DIRECTORS":




=>
• die Personalstruktur ist viel zu Europa-lastig
• auch ist der Order backlog recht lau (*)
• Kupfer ist hier das maßgebliche Metall, und zwar mit Abstand


(*) das ist interessant, da es auch heißen könnte, daß bei den betreffenden Rohstoffen es weiter Preisauftrieb geben könnte, da die Kunden von Outotec sich mit Aufträgen wiederholt zurückhalten. Stichwort: Kapazitäten
Antwort auf Beitrag Nr.: 59.931.599 von faultcode am 21.02.19 13:34:41
Outotec to deliver sulfuric acid plant to Morocco
https://www.wallstreet-online.de/nachricht/11305794-outotec-…

=>
...Outotec has signed a contract with the Moroccan OCP Group for the delivery of a sulfuric acid plant for fertilizer production. The approximately EUR 80 million order has been booked into Outotec's 2019 first quarter order intake.

Outotec's delivery includes the engineering, procurement and construction of the plant, which is based on Outotec's sulfur burning system. The new acid plant will incorporate advanced proprietary technologies such as HEROS heat recovery system as well as a converter, absorption towers and an acid distribution system that are made of the Edmeston SX stainless steel alloy.

With more than 20 acid plants and several mining sites, OCP Group is a global fertilizer producer and leader in the phosphate industry. The acid plant will be built in connection with their existing chemical complexes and support in OCP's fertilizer production from phosphate rock from their mining processes as a raw material.

"Outotec's sulfuric acid technology has proven to be one of the leading technologies for decades. We are honored that OCP has selected our design for their new plant. With our leading technologies providing benefits such as safety, high reliability and enhanced heat recovery we are happy to help OCP reach their sustainability targets," says Kalle Härkki, head of Outotec's Metals, Energy & Water business...
Antwort auf Beitrag Nr.: 60.087.504 von faultcode am 13.03.19 11:26:19
Outotec awarded a pellet plant expansion contract by JSC Stoilensky GOK in Russia
https://www.wallstreet-online.de/nachricht/11342867-outotec-…

=>
...Outotec and Russian iron ore pellet producer JSC Stoilensky GOK (S-GOK), which is a part of NLMK Group, have entered into a contract to expand S-GOK's pellet plant located in Stary Oskol, Russia. The approximately EUR 15 million order has been booked in Outotec's 2019 first quarter order intake.

Outotec has delivered the technology for S-GOK's pellet plant (press release September 12, 2011), which has been in operation since 2017. The annual capacity of the pellet plant will be increased from 6 to 8 million tonnes. Outotec will be responsible for the engineering, supply of key equipment and automation system as well as advisory services for installation and commissioning of the expansion. Outotec's latest technology improvements in green pelletizing, cooling air process, and pallet car changing system will be applied, together with a digital solution package. Outotec's deliveries will take place at the end of 2020...
Saudi Arabian Mining Company (Ma'aden) awarded Outotec a EUR 140 million gold processing plant order
ganz dicker Auftrag und sehr wichtig --> heißt das doch, daß die Sache mit dem Ofen doch nicht so schlimm ist, um einen anderen Großauftrag in Saudi Arabia zu blockieren:


https://www.wallstreet-online.de/nachricht/11417822-saudi-ar…

=>
...In a major international competitive bidding process, the Saudi Arabian Mining Company (Ma'aden) has awarded the consortium of Outotec and Larsen & Toubro with an engineering, procurement and construction contract to build a greenfield mineral concentrator and gold processing plant in the Kingdom of Saudi Arabia.

Outotec's share of the project is over EUR 140 million. The order is almost evenly shared between the reporting segments and will be booked into Outotec's second quarter 2019 order intake. The total value of the project is approximately EUR 540 million...


Outotec's delivery includes basic and detail engineering, procurement and delivery of process equipment, commissioning, start-up assistance and training services. The new gold processing plant is due to be completed in 2022. Ma'aden is the champion of the Saudi Arabian mining industry, and now internationally recognized mining company with global presence.

The Mansourah & Massarah mines and processing plant will be built in the Central Arabian gold region. The processing plant will be capable of processing up to four million tonnes of ore per annum. The concentrator and the gold processing plant is designed producing an average of 250,000 ounces of gold per year over the life of mine...
Antwort auf Beitrag Nr.: 60.515.757 von faultcode am 08.05.19 13:01:35
Outotec to deliver a mine paste backfill system to Australia
https://www.wallstreet-online.de/nachricht/11458247-outotec-…

=>
...Outotec has been awarded a contract to design and deliver a mine paste backfill system to OZ Minerals' Prominent Hill mine. The contract price is EUR 15 million and it has been booked into Outotec's 2019 second quarter order intake.

Outotec's supply includes the design and delivery of a complete paste backfill system as well as detailed design of the underground distribution network and fill management systems. The new paste backfill plant will be based on a unique process design, which allows flexibility to use continuously produced fresh tailings or store filter cake to meet the future backfill needs of the underground mining operation.

The new facility is expected to have a capacity of 215 m3 per hour...