Energiekontor AG: Energiekontor with strong operational momentum in the first nine months of 2025 – project progress confirms strong basis for continued growth
- Energiekontor shows strong growth in 2025, despite challenges.
- 17 projects under construction, boosting capacity to 611 MW.
- Adjusted earnings forecast reflects external project delays.
|
EQS-News: Energiekontor AG / Key word(s): 9 Month figures Energiekontor with strong operational momentum in the first nine months of 2025 – project progress confirms strong basis for continued growth |
Bremen, 13 November 2025 – Energiekontor AG (“Energiekontor”), a leading German project developer and operator of wind and solar parks based in Bremen and listed in the General Standard, has consistently continued its operational growth course in the first nine months of 2025. Despite the adjusted earnings forecast for the current financial year in October 2025, operational development is showing exceptionally strong momentum. Numerous projects have been approved, awarded and brought to financial close in recent months. The high realisation rate and solid project base demonstrate the sustainable strength of Energiekontor's business model and form the basis for further growth in the coming years.
In the first nine months of 2025, Energiekontor sold five wind projects with a combined generation capacity of around 115 megawatts. These included the Hare Craig ready-to-build project in the United Kingdom, sold to Uniper; the Würselen wind park, which was repowered and commissioned in May 2025 before being sold to SachsenEnergie; and three turnkey projects in North Rhine-Westphalia. With these transactions, Energiekontor is once again demonstrating the strength of its business model across various markets. In addition, further project sales are at an advanced stage of negotiation, some of which are expected to be completed in the current financial year.
As of 30 September 2025, 17 projects with a total generating capacity of around 552 megawatts were under construction or being prepared for construction. Of these, seven projects, with a combined capacity of around 200 megawatts, will be added to Energiekontor’s own portfolio once commissioned. Following the reporting date, financial close was also achieved for two German wind park projects, Wulkow-Booßen and Nideggen, bringing the number of projects under construction to 19 with a total capacity of approximately 611 megawatts. Energiekontor's construction activity thus stands at an all-time high, demonstrating its continued strength in realisation within the German and international project development business.