GoGold Advances Los Ricos South Construction
Halifax, Nova Scotia--(Newsfile Corp. - September 22, 2026) - GoGold Resources Inc. (TSX: GGD) (OTCQX: GLGDF) ("GoGold", "the Company") is pleased to provide an update on construction at its Los Ricos South project in Jalisco, Mexico, following the commencement announced on August 25, 2026. The project is progressing on schedule, and the Company reiterates first silver pour in the second quarter of 2028.
"Construction at Los Ricos South is moving ahead at full steam. Site clearing is well advanced, with more than 150 contractors on site, and all long-lead equipment orders have been placed," said Brad Langille, President and CEO. "With US$284 million in cash in addition to cash flow from Parral, the project is fully funded with no debt or additional equity required. Based on our internal estimates using $60/oz silver and $4,200/oz gold, we see our maximum cash outlay in Q3 2027 and maintain cash reserves at a minimum of US$130 million throughout the build. We are progressing on schedule and remain focused on delivering first silver pour in Q2 2028."
Los Ricos South Construction Highlights
-
Active site works - Site clearing and earthworks advancing at the process plant site with more than 150 contractors on site.
-
All long-lead orders placed - All long-lead equipment orders have been placed, with procurement continuing on schedule. The long-lead orders include the SAG mill, tailings filter, crusher, electrical switchgear, Merrill-Crowe plant, conveyors, slurry pumps, hydrocyclones, feeders and screens.
-
Plant design - the design by M3 and DENM Engineering is at 90% complete
-
Underground mining contractor selected - Cominvi planned to mobilize to site in Q4 2026.
-
Schedule maintained - Construction and procurement remain on schedule, with first silver pour reiterated for Q2 2028.
To date, the Company has spent US$15 million on the project. Following are the key schedule milestones:
Los Ricos South Key Schedule Milestones
- Earthworks commenced - August 2026
- Underground mine plan optimization commenced - August 2026
- Start of powerline installation - November 2026
- Concrete foundation pouring - January 2027
- Portal development / ramp blasting - January 2027
- Paste plant construction begins - January 2027
- Hill-slope stabilization / mining - Main/Abra zone - March 2027
- SAG mill delivery to site - May 2027
- Plant commissioning begins - January 2028