Red Metal Provides Farellon Mining Update
Vancouver, British Columbia--(Newsfile Corp. - October 14, 2026) - RED METAL RESOURCES LTD. (CSE: RMES) (OTC: RMESF) (FSE: I660) ("Red Metal" or the "Company") is pleased to provide a mining update for the Farellon Project at its Carrizal Copper-Gold-Cobalt Property ("Carrizal" or the "Property") near Vallenar, Chile. The lessee and operator, Minera KMT SpA ("KMT"), has received final settlements from the Empresa Nacional de Minería ("ENAMI") for its August and September 2026 deliveries of copper sulphide and gold ore to ENAMI's Vallenar plant, and has advanced underground development from Level 7 to Level 9 of the north portal.
Highlights
-
Two Months of ENAMI Settlements: 1,042 tonnes of Farellon ore settled for August and September
-
Grades Nearly Double: September copper and gold grades nearly doubled as mining moved deeper
-
Development Reaches Level 9: Approximately 115 metres of underground development completed
ENAMI Settlement Results – August and September 2026
KMT delivered 16 lots totalling 597 tonnes to ENAMI's Vallenar plant on August 20 and 21, 2026 (see news release dated September 3, 2026), and a further 13 lots totaling 471 tonnes closed on September 15, 2026. ENAMI has now issued its final settlements for both months. The results are summarized in Table 1.
Table 1 – ENAMI settlement summary August and September 2026
| Month delivered | Lots | Wet tonnes | Dry tonnes |
Cu insoluble (%) |
Au (g/t) |
Contained Cu (kg) |
Contained Au (g) |
| August 2026 | 16 | 597.6 | 582.2 | 0.66 | 0.19 | 3,818 | 111 |
| September 2026 | 13 | 471.3 | 460.0 | 1.26 | 0.31 | 5,785 | 141 |
| Total / weighted average | 29 | 1,068.9 | 1,042.3 | 0.92 | 0.24 | 9,603 | 253 |