     202  0 Kommentare Northern Gold Submits Garrcon Advanced Exploration Closure Plan

    TORONTO, ONTARIO--(Marketwired - May 7, 2014) - NORTHERN GOLD MINING INC. (TSX VENTURE:NGM) ("Northern Gold" or the "Company") is pleased to announce that it has submitted an advanced exploration mine closure plan ("Closure Plan"), to the Ministry of Northern Development and Mines ("MNDM") to remove up to 150,000 tonne bulk sample from its wholly owned Garrcon Gold Deposit, located on the Garrison Property. The Garrison Property is Northern Gold's flagship property within its Golden Bear Project, located 100 km east of Timmins, Ontario.

    The application for an Advanced Exploration permit requires that a Closure Plan be submitted under Part VII Sections 11-12 of the Mining Act. The Closure Plan is a document that describes the work completed to date, the scope of work that is to occur at the mine site as well as environmental baseline data, engineering data related to the mine development and rehabilitation measures to be taken if the project is discontinued. The document includes studies describing the local water resources, terrestrial and aquatic surveys, geochemistry, local hydrology including the installation of monitoring wells, geotechnical drilling and rock stability studies.

    Blue Heron Environmental of Timmins, Ontario was responsible for the preparation of the report which included studies prepared by Blue Heron Environmental, Golder Associates and Terrane Geoscience.

    In January of 2014 Northern Gold held public consultation meetings in the Town of Matheson and at nearby Wahgoshig First Nation. Both events received positive support for the project.

    In conjunction with the filing of the Closure Plan the Company has submitted financial assurance to the MNDM to cover the cost of project rehabilitation as required by the Mining Act. The financial assurance can be reimbursed after the completion of rehabilitation and project close out as outlined in the Closure Plan.

    The MNDM has up to 45 days to review the Closure Plan and upon approval by the Company will have the necessary permits excavate up to a 150,000 tonne bulk sample for offsite processing. The Company feels that this scale of development will be capable of demonstrating the economic potential of the Garrcon deposit. The test mining to be conducted over the summer of 2014 will allow for better definition of project data inputs to be used in a future feasibility study. The Company will focus on collecting data related to bulk metallurgical characteristics, geotechnical parameters, block model reconciliation, blasting techniques and grade controls.

    Seite 1 von 3




    Verfasst von Marketwired
    Northern Gold Submits Garrcon Advanced Exploration Closure Plan TORONTO, ONTARIO--(Marketwired - May 7, 2014) - NORTHERN GOLD MINING INC. (TSX VENTURE:NGM) ("Northern Gold" or the "Company") is pleased to announce that it has submitted an advanced exploration mine closure plan ("Closure Plan"), to the Ministry …