checkAd

    Eramet Group  426  0 Kommentare GRANDE CÔTE (SENEGAL) UPDATE

                                                                                          

    Paris, August 20, 2014

     

    PRESS RELEASE

    GRANDE CÔTE (SENEGAL) UPDATE

     

    ERAMET group provides hereunder the content of today's release to the Oslo stock exchange by TiZir, a company jointly held at 50/50 by ERAMET with Mineral Deposits Limited (Australia), with regards to the Grande Côte project in Senegal.

    Lesen Sie auch

    The impact of this situation on the ERAMET Group's 2014 results should remain limited.


    ABOUT ERAMET

    ERAMET is a leading global producer of:

    • alloying metals, particularly manganese and nickel, used to improve the properties of steel,
    • high-performance special steels and alloys used in industries such as aerospace, power generation and tooling.

    ERAMET has major research and development projects in new business lines with high growth potential, such as mineral sands (titanium dioxide and zircon), lithium, niobium and rare earths, and in recycling.

    The Group employs approximately 14,000 people in 20 countries. ERAMET is part of Euronext Paris Compartment A.

    CONTACT

    Head of Financial Communications and Economic Studies

    Philippe Joly

    Tel: +33 (0)1 45 38 42 02

     

    Investor Relations and Economic Analyst

    David Fortin

    Tel: +33 (0)1 45 38 42 86

     

    For more information: www.eramet.com


     

     

     

     20 August 2014

     

     

    TiZir Grande Côte Update

     

    TiZir advises that due to the failure of successive impellors within the main dredge pump, mining operations at Grande Côte in Senegal are currently suspended pending a site investigation early next week. It is anticipated that mining will be restarted at that time and proceed on a reduced basis.

    The last of the currently available spare impellors is showing signs of failure. Extensive work is being undertaken in conjunction with suppliers and ERAMET's Research and Development personnel to determine the cause of the failures and to manage the lifespan of the present impellor in order to sustain mining operations. At this stage it is not known whether the failures are due to a casting fault, a design fault or an operational fault. It is however, unlikely that the current impellor will last until early October when the first of a number of pre-ordered replacement impellors is expected on site.

    Given the significant progress that has been made with the ramp-up of Grande Côte, the impellor failures are obviously a disappointing setback. We are confident, however, that the underlying problem will be identified and resolved.

     

     

    TiZir Limited | 33 Cavendish Square, London W1G 0PW United Kingdom

    T:+44 207 182 4200 | E: info@tizir.co.uk | W: www.tizir.co.uk

     






    This announcement is distributed by NASDAQ OMX Corporate Solutions on behalf of NASDAQ OMX Corporate Solutions clients.
    The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
    Source: Groupe Eramet via Globenewswire

    HUG#1850150


    Diskutieren Sie über die enthaltenen Werte


    GlobeNewswire
    0 Follower
    Autor folgen

    Verfasst von GlobeNewswire
    Eramet Group GRANDE CÔTE (SENEGAL) UPDATE                                                                                        Paris, August 20, 2014   PRESS RELEASE GRANDE CÔTE (SENEGAL) UPDATE   …

    Schreibe Deinen Kommentar

    Disclaimer