VANCOUVER, BC / ACCESSWIRE / March 28, 2024 / Temas Resources Corp. ("Temas" or the "Company") (CSE:TMAS) is pleased to report the filing of an Independent Technical Report and Preliminary Economic Assessment ("PEA") on SEDAR+ for the wholly-owned …
VANCOUVER, BC / ACCESSWIRE / March 28, 2024 / Temas Resources Corp. ("Temas" or the "Company") (CSE:TMAS) is pleased to report the filing of an Independent Technical Report and Preliminary Economic Assessment ("PEA") on SEDAR+ for the wholly-owned La Blache Ti-V-Fe Project located in the Cote Nord region of Quebec (the "Project").
Material changes occurred to the Project economics between February 7, 2024, the date the news release first announcing the PEA, and today, the date the PEA was finalized and posted on SEDAR+.
Lesen Sie auch
A summary of the material changes to the primary project economic indicators are presented in the table below. The full PEA report on SEDAR+ presents complete descriptions and lists of all assumptions used.
Primary La Blache Project Economic Indicators |
Press Release |
PEA |
|
February 27, 2024 |
March 27, 2024 |
||
Parameter |
Units |
Value |
Value |
Pre-Tax Project Cash Flow |
CAD $ Billion |
21.8 |
20.2 |
Pre-Tax IRR |
% |
64.8 |
70.8 |
Pre-Tax Net Present Value (NPV8) |
CAD $ Billion |
9.5 |
9.0 |
Post-Tax Project Cash Flow |