checkAd

     582  0 Kommentare SilverCrest Announces Completion of Mill Commissioning Major Milestone Achieved as Growth Continues

    VANCOUVER, BRITISH COLUMBIA--(Marketwired - Aug. 11, 2014) - SilverCrest Mines Inc. (the "Company") (TSX:SVL)(NYSE MKT:SVLC) is pleased to announce that the new 3,000 tonne- per-day ("tpd") mill and facilities (CCD-Merrill Crowe recovery) at its 100% owned Santa Elena Mine has been successfully commissioned. The commissioning period began in early May, 2014, and planned for 3 months of ramp-up, which was completed as of August 1, 2014. The Santa Elena Mine is currently transitioning from an open pit heap leach operation to a conventional 3,000 tpd conventional mill facility and underground operation. For additional information and to view photos and videos, please visit the Company's website at www.silvercrestmines.com.

    N. Eric Fier, President and COO stated; "The announcement of commissioning completion for the new Santa Elena mill and facilities is another major milestone achieved as SilverCrest continues systematic and responsible growth. Our dedicated construction, commissioning and operating teams should be congratulated on their continued efforts toward achieving targets under strict schedules and cash control protocols. We will continue to adjust and optimize all the components of the facilities in efforts to achieve through-put tonnages at or above the nameplate capacity of 3,000 tpd. Our near term focus now turns to achieving further milestones, including underground stope production in August and free cash flow in Q3, 2014."

    In determining commissioning completion, management considered the following criteria;

    • Achieving greater than 80% of nameplate capacity (3,000 tpd) over a reasonable period of continuous production.
    • Achieving average startup recovery rates of 82% gold and 65% silver. Average mine life recovery rates are projected at 92% gold and 67.5% silver.
    • Dore production from the new mill exceeding budget estimates.
    • All major components of the mill and facilities completed and operating to the satisfaction of management and independent commissioning team.
    • Completion of budgeted capital expenditures.
    • Achieving positive operating cash flows from expanded operations including mill.

    For 30 continuous days through to early August, 2014, the mill through-put ranged from 1,485 to 3,144 tpd and achieved an average of 2,524 tpd or 84% of the 3,000 tpd nameplate capacity. In July, 1,516 ounces of gold and 81,818 ounces of silver (excluding residual leached ounces from pad production) were produced and which exceeded budgeted production of 1,255 ounces of gold and 74,325 ounces of silver. Startup recoveries of gold and silver in July were 82% and 65%, respectively, compared to budgeted start up recoveries of 83% and 62%. All of the above commissioning criteria have been met to the satisfaction of management.

    Seite 1 von 4




    Verfasst von Marketwired
    SilverCrest Announces Completion of Mill Commissioning Major Milestone Achieved as Growth Continues VANCOUVER, BRITISH COLUMBIA--(Marketwired - Aug. 11, 2014) - SilverCrest Mines Inc. (the "Company") (TSX:SVL)(NYSE MKT:SVLC) is pleased to announce that the new 3,000 tonne- per-day ("tpd") mill and facilities (CCD-Merrill Crowe recovery) at its …