     557  0 Kommentare Pretivm Reports First Quarter 2016 Results - Seite 2

    The foundation for the 330-person camp at Brucejack is complete and the installation of prefabricated modules for the camp is underway. The camp is expected to be operational early in the third quarter of this year.

    Excavation to level the site for the mill facility has been completed, and concrete works are well underway. The structural steel installation for the mill building is scheduled to begin in June, with full enclosure of the mill building expected in the third quarter. Installation of internal structural steel and mechanical equipment will commence prior to full enclosure.

    Surface excavation for the Valley of the Kings portal pad advanced during the quarter. The portal will serve as the primary access point to convey the gold ore from the underground crusher to the mill.

    Underground development remains on schedule and crews are advancing at a rate of over 20 meters a day. Current underground activity at the Valley of the Kings includes excavation of the 1260-meter level ramp, development of the 1320-meter level, installation of ladderways and platforms in the fresh air raise and the excavation of headings for infrastructure.

    The transmission line towers have begun arriving at site from the fabricator and installation will be ongoing throughout the second and third quarters, with connection to the BC Hydro power grid expected in the fourth quarter.

    Project Engineering and Procurement

    Detailed project engineering is ongoing. All long lead-time items have been ordered, including the ball and SAG mills which are scheduled to arrive on site in the third quarter.

    Project Financing

    On September 21, 2015, we completed a US$540 million construction financing with Orion Mine Finance Group and Blackstone Tactical Opportunities. The financing was comprised of a credit facility for US$350 million, a US$150 million prepayment under a callable gold and silver stream agreement and a private placement of our common shares for US$40 million.

    During the first quarter, on February 22, 2016, we announced the filing of a preliminary prospectus supplement to our short form base shelf prospectus in connection with a US$120 million marketed offering of our common shares through a syndicate of underwriters. On February 23, 2016, we announced the underwriters had agreed to purchase 26,210,000 of our common shares at US$4.58 per share, for gross proceeds of approximately US$120 million. The underwriters were also granted an over-allotment option to purchase an additional 2,174,000 common shares at US$4.58 per share, exercisable for a period of 30 days following closing. On March 1, 2016, we announced the closing of the marketed offering of our common shares for gross proceeds of approximately US$130 million, which included the exercise of the over-allotment option.

    Seite 2 von 5




    Verfasst von Marketwired
    Pretivm Reports First Quarter 2016 Results - Seite 2 VANCOUVER, BRITISH COLUMBIA--(Marketwired - May 12, 2016) - Pretium Resources Inc. (TSX:PVG)(NYSE:PVG) ("Pretivm" or the "Company") is pleased to report the following highlights from the first quarter of 2016 and updates for its high-grade gold …