checkAd

    MONUMENT Mining Ltd. (WKN: A0MSJR) Goldproduzent aus Kanada!!!!!!!!!!!!!!!! - Älteste Beiträge zuerst (Seite 2406)

    eröffnet am 18.07.07 20:46:05 von
    neuester Beitrag 17.01.24 11:14:47 von
    Beiträge: 28.400
    ID: 1.130.522
    Aufrufe heute: 0
    Gesamt: 2.912.672
    Aktive User: 0

    ISIN: CA61531Y1051 · WKN: A0MSJR · Symbol: MMY
    0,1500
     
    CAD
    -3,23 %
    -0,0050 CAD
    Letzter Kurs 03.05.24 TSX Venture

    Werte aus der Branche Rohstoffe

    WertpapierKursPerf. %
    9,8360+17,66
    1,0950+16,00
    2,4000+14,83
    552,55+13,76
    33,17+13,52
    WertpapierKursPerf. %
    185,00-9,76
    0,7000-11,39
    0,6700-14,92
    43,97-16,90
    12,000-25,00

     Durchsuchen
    • 1
    • 2406
    • 2840

    Begriffe und/oder Benutzer

     

    Top-Postings

     Ja Nein
      Avatar
      schrieb am 28.07.14 23:24:07
      Beitrag Nr. 24.051 ()


      http://online.wsj.com/article/PR-CO-20140728-909998.html


      "Monument Updates on Selinsing Phase IV Development and Selinsing Litigation

      Release #20 - 2014

      Vancouver, B.C., July 28, 2014, Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) "Monument" or the "Company" provides an update on its Selinsing Phase IV development to treat its transition and sulphide material and the most recent developments in respect of previously disclosed litigation concerning a purported joint venture interest in the Selinsing project.

      Selinsing R&D - Phase IV Sulphide Biological Oxidation Treatment Programs

      Independent metallurgical testing conducted by Inspectorate Exploration and Mining Services in Canada was performed on refractory sulphide ore samples from the Selinsing Deeps and Buffalo Reef projects. The test work encompassed a variety of methods including pressure oxidation, ultrafine grinding, roasting and acid leaching techniques.

      The best recoveries for sulphide ore were achieved in the mid to upper 80% range with a biological oxidation approach through a combined flotation and tank bioleach treatment approach. The processing facilities would require a capital investment of approximately US$50.0 million, according to an engineering study carried out by Lycopodium of Australia, and an additional estimated cost of US$10.0 million for a new power line being built with an estimated completion time of 2 to 3 years.

      A follow-up engineering study performed by Tetratech in Canada shows that some savings could be realized by incorporating a modified design. Management is continuing its research and development work in evaluating less capital intensive alternatives.

      One such option currently forwarded for testing is biological heap leaching. The biological heap leach approach is aimed to use acid produced from sulphide minerals in the ore to stimulate the natural occurrence of soil microbes in dissolving sulphides contained in the ore materials. Once the sulphides are dissolved in the leach pads, the oxidized sulphide ore would be further leached in the same pads or in the existing comminution and CIL circuit. This would be then followed by smelting into dore bars for shipping to a refinery as is performed at present for oxide ore.

      The biological heap leach method has the advantage of low capital investment. A sulphide concentration plant and alterations to crush ore feed would not be required under this method. Potentially crushed ore from the present crushing circuit can be directly treated though permanent heap leach pads. These permanent re-usable heap leach pads can be built and operated in-house by the present staffing at Selinsing with low capital expenditure that require multiple cells, suitably lined liquor ponds and a network of reticulation piping, pumps and metal recovery systems. While recoveries of gold product can be lower than bioleach treatment plant, potential heap leach issues such as heap blinding and slumping can be minimized by methods such as whole ore stacking, de-sliming, eliminating agglomeration and other approaches currently being considered.

      There is an adequate area of suitable land to construct heap leach cells and ponds on site and a plentiful supply of limestone at Selinsing is available for neutralizing the solutions prior to discharge to the tailing containment facility.

      The present research and development programs on various alternate oxidation processes will continue to completion in parallel with these heap leach trials before a final commercial decision is made. Once a viable method is identified as satisfactory and is signed off by a qualified person, the Company expects to complete and publish an updated technical report prepared in accordance with National Instrument 43-101.

      In the meantime, the Company will continue to feed the Selinsing gold plant with the low grade oxide stockpile and the stockpiled materials discharged from the mill in the early stage of the production, totalling approximately 3,000,000 tonnes while the leach trials on sulphide ore are conducted.

      The information in this section has been compiled, reviewed and approved by Michael John Kitney who is a member of the Australasian Institute of Mining & Metallurgy. Michael Kitney is a qualified Metallurgist retained by Monument Mining Limited and is a Qualified Person as defined by JORC guidelines and NI43-101. He has been working in Australia for Monument as an independent consultant.

      Selinsing Litigation Update – Selinsing Mine Sdn Bhd (the “Plaintiff”) VS Selinsing Gold Mine Manager Sdn Bhd, Able Return Sdn Bhd and Monument Mining Limited (“SMSB VS Monument”) in a Claim for 5% JV interest in Selinsing

      A full trial of the matter has been fixed at the Shah Alam High Court, Malaysia in October 2014 after the Court of Appeal set aside with cost in July 2013 a summary judgment which was granted by Shah Alam High Court in March 2013 in favour of the Plaintiff against Monument, including a conditional stay of the summary judgment for Monument to pay cash of approximately US$10 million into a bank account jointly operated by both parties solicitors.

      However, the Plaintiff recently filed another application to the Shah Alam High Court for an interim injunctive relief, including, among other things, restraining and preventing Monument’s wholly-owned subsidiary, Selinsing Gold Mine Manager Sdn Bhd from disposing of and/or transferring the Plaintiff’s purported 5% share of the profits obtained from the Selinsing Mine to Monument’s wholly-owned subsidiary, Able Return Sdn Bhd, Monument or other third parties pursuant to the purported joint venture agreement claimed by the Plaintiff, and ordering that US$9.4 M be deposited within 30 days into a joint account to be maintained by legal counsel of the respective parties to the lawsuit, pending the hearing and determination from the coming full trial. The injunctive relief was granted by the Shah Alam High Court.

      Monument has not yet received the written court order and accordingly the grounds upon which the injunctive relief was granted are not known and unclear to the Company at this time. Monument filed an appeal to the Court of Appeal in Putrajaya on July 23 2014 and also filed an application with the Shah Alam High Court on July 25 2014 for a stay of the injunction order. The Company maintains its view, based on legal advice and the facts of the matter that the claim by the Plaintiff is without merit.

      Shah Alam High Court has also granted among others an injunction order restraining SMSB from interfering and disrupting the management of the business operation on MC 1/113 and MC 1/124 and from corresponding with any third parties on the subject matter.

      Background: On October, 10, 2012, the Plaintiff, Selinsing Mine Sdn Bhd, a company wholly owned by Kesit Pty Ltd, an Australian private limited company owned and controlled by Peter Steven Kestel and his wife filed a Writ and Statement of Claim against Monument and its wholly-owned subsidiaries, Selinsing Gold Mine Manager Sdn Bhd and Able Return Sdn Bhd. The Plaintiff in the suit claimed, among other things, a 5% “Joint Venture interest” in the profit of the gold production from one of tenements of Monument’s Selinsing Gold Mine. The Plaintiff was the previous sub-lease holder and operator that sold the Selinsing Gold Mine to Monument and its subsidiaries free and clear of any encumbrances. The transaction was closed on June 25, 2007 and the Plaintiff has been paid in full. The claim against Monument and its subsidiaries was not made until 2012 in relation to the Plaintiff’s purported “Joint Venture interest”. Monument denies that the Plaintiff has any joint venture interest in the Selinsing Gold Mine and intends to continue to vigorously defend this claim. (...)"
      Avatar
      schrieb am 28.07.14 23:36:32
      Beitrag Nr. 24.052 ()
      Gibt ein paar news zu Monument Mining

      Dear Subscriber,

      July 28 2014

      Monument Updates on Selinsing Phase IV Development and Selinsing Litigation

      Release #20 - 2014

      Vancouver, B.C., July 28, 2014, Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) "Monument" or the "Company" provides an update on its Selinsing Phase IV development to treat its transition and sulphide material and the most recent developments in respect of previously disclosed litigation concerning a purported joint venture interest in the Selinsing project.

      Selinsing R&D - Phase IV Sulphide Biological Oxidation Treatment Programs

      Independent metallurgical testing conducted by Inspectorate Exploration and Mining Services in Canada was performed on refractory sulphide ore samples from the Selinsing Deeps and Buffalo Reef projects. The test work encompassed a variety of methods including pressure oxidation, ultrafine grinding, roasting and acid leaching techniques.

      The best recoveries for sulphide ore were achieved in the mid to upper 80% range with a biological oxidation approach through a combined flotation and tank bioleach treatment approach. The processing facilities would require a capital investment of approximately US$50.0 million, according to an engineering study carried out by Lycopodium of Australia, and an additional estimated cost of US$10.0 million for a new power line being built with an estimated completion time of 2 to 3 years.

      A follow-up engineering study performed by Tetratech in Canada shows that some savings could be realized by incorporating a modified design. Management is continuing its research and development work in evaluating less capital intensive alternatives.

      One such option currently forwarded for testing is biological heap leaching. The biological heap leach approach is aimed to use acid produced from sulphide minerals in the ore to stimulate the natural occurrence of soil microbes in dissolving sulphides contained in the ore materials. Once the sulphides are dissolved in the leach pads, the oxidized sulphide ore would be further leached in the same pads or in the existing comminution and CIL circuit. This would be then followed by smelting into dore bars for shipping to a refinery as is performed at present for oxide ore.

      The biological heap leach method has the advantage of low capital investment. A sulphide concentration plant and alterations to crush ore feed would not be required under this method. Potentially crushed ore from the present crushing circuit can be directly treated though permanent heap leach pads. These permanent re-usable heap leach pads can be built and operated in-house by the present staffing at Selinsing with low capital expenditure that require multiple cells, suitably lined liquor ponds and a network of reticulation piping, pumps and metal recovery systems. While recoveries of gold product can be lower than bioleach treatment plant, potential heap leach issues such as heap blinding and slumping can be minimized by methods such as whole ore stacking, de-sliming, eliminating agglomeration and other approaches currently being considered.

      There is an adequate area of suitable land to construct heap leach cells and ponds on site and a plentiful supply of limestone at Selinsing is available for neutralizing the solutions prior to discharge to the tailing containment facility.

      The present research and development programs on various alternate oxidation processes will continue to completion in parallel with these heap leach trials before a final commercial decision is made. Once a viable method is identified as satisfactory and is signed off by a qualified person, the Company expects to complete and publish an updated technical report prepared in accordance with National Instrument 43-101.

      In the meantime, the Company will continue to feed the Selinsing gold plant with the low grade oxide stockpile and the stockpiled materials discharged from the mill in the early stage of the production, totalling approximately 3,000,000 tonnes while the leach trials on sulphide ore are conducted.

      The information in this section has been compiled, reviewed and approved by Michael John Kitney who is a member of the Australasian Institute of Mining & Metallurgy. Michael Kitney is a qualified Metallurgist retained by Monument Mining Limited and is a Qualified Person as defined by JORC guidelines and NI43-101. He has been working in Australia for Monument as an independent consultant.

      Selinsing Litigation Update – Selinsing Mine Sdn Bhd (the “Plaintiff”) VS Selinsing Gold Mine Manager Sdn Bhd, Able Return Sdn Bhd and Monument Mining Limited (“SMSB VS Monument”) in a Claim for 5% JV interest in Selinsing

      A full trial of the matter has been fixed at the Shah Alam High Court, Malaysia in October 2014 after the Court of Appeal set aside with cost in July 2013 a summary judgment which was granted by Shah Alam High Court in March 2013 in favour of the Plaintiff against Monument, including a conditional stay of the summary judgment for Monument to pay cash of approximately US$10 million into a bank account jointly operated by both parties solicitors.

      However, the Plaintiff recently filed another application to the Shah Alam High Court for an interim injunctive relief, including, among other things, restraining and preventing Monument’s wholly-owned subsidiary, Selinsing Gold Mine Manager Sdn Bhd from disposing of and/or transferring the Plaintiff’s purported 5% share of the profits obtained from the Selinsing Mine to Monument’s wholly-owned subsidiary, Able Return Sdn Bhd, Monument or other third parties pursuant to the purported joint venture agreement claimed by the Plaintiff, and ordering that US$9.4 M be deposited within 30 days into a joint account to be maintained by legal counsel of the respective parties to the lawsuit, pending the hearing and determination from the coming full trial. The injunctive relief was granted by the Shah Alam High Court.

      Monument has not yet received the written court order and accordingly the grounds upon which the injunctive relief was granted are not known and unclear to the Company at this time. Monument filed an appeal to the Court of Appeal in Putrajaya on July 23 2014 and also filed an application with the Shah Alam High Court on July 25 2014 for a stay of the injunction order. The Company maintains its view, based on legal advice and the facts of the matter that the claim by the Plaintiff is without merit.

      Shah Alam High Court has also granted among others an injunction order restraining SMSB from interfering and disrupting the management of the business operation on MC 1/113 and MC 1/124 and from corresponding with any third parties on the subject matter.

      Background: On October, 10, 2012, the Plaintiff, Selinsing Mine Sdn Bhd, a company wholly owned by Kesit Pty Ltd, an Australian private limited company owned and controlled by Peter Steven Kestel and his wife filed a Writ and Statement of Claim against Monument and its wholly-owned subsidiaries, Selinsing Gold Mine Manager Sdn Bhd and Able Return Sdn Bhd. The Plaintiff in the suit claimed, among other things, a 5% “Joint Venture interest” in the profit of the gold production from one of tenements of Monument’s Selinsing Gold Mine. The Plaintiff was the previous sub-lease holder and operator that sold the Selinsing Gold Mine to Monument and its subsidiaries free and clear of any encumbrances. The transaction was closed on June 25, 2007 and the Plaintiff has been paid in full. The claim against Monument and its subsidiaries was not made until 2012 in relation to the Plaintiff’s purported “Joint Venture interest”. Monument denies that the Plaintiff has any joint venture interest in the Selinsing Gold Mine and intends to continue to vigorously defend this claim.

      About Monument

      Monument Mining Limited (TSX-V: MMY, FSE:D7Q1) is an established Canadian gold producer that owns and operates the Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is advancing several exploration and development projects in Malaysia and Australia, including the development stage, Mengapur Polymetallic Project in Malaysia and the Murchison Project in Western Australia. The Company employs approximately 300 people and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.

      Robert F. Baldock, President and CEO
      Monument Mining Limited
      Suite 1580, 1100 Melville Street
      Vancouver B.C. Canada V6E 4A6
      Avatar
      schrieb am 29.07.14 09:59:42
      Beitrag Nr. 24.053 ()
      Suuuuper Nachrichten! Paßt zur Strategie dieses Jahr.Die möglichen positiven Nachrichten zurückhalten und alles schlechte rausbrigen. Kur runter bringen und dann ein schönes fettes PP am besten zu 0,20 CAD an einen malayischen Investor, mit der Begründung das man ja noch unbedingt Geld braucht.

      Ich hoffe nur das dann genügend Leute dabei sind bei einer Sammelklage....ist ja dann nichts neues für MMY!
      Avatar
      schrieb am 29.07.14 12:51:48
      Beitrag Nr. 24.054 ()
      Hm wahrscheinlich stimmen die Positiven Rechnungen zu Mengapur und man möchte so viele Kleininvestoren wie möglich raus haben und dann den Kuchen untereinander aufteilen.

      Das ist definitiv nicht normal im März sollte die Machbarkeitstudie fertig sein bis jetzt nicht und auch die Recourcenschätzung nichts obwohl man da vllt noch bis zum Gerichtsprozess wartet. Aber selbst wenn man noch vllt andere Recourcen mit in die Studie nehmen möchte könnte das Managment das sagen.

      Nur mal so mein Frust ablassen
      Avatar
      schrieb am 29.07.14 13:27:04
      Beitrag Nr. 24.055 ()
      So dumm kann doch keiner sein und sowas in einem Vertrag zu übersehen???

      was würde MMY eine Niederlage kosten??

      100-150 mio Gewinn hat Selinsing bis jetzt ca. abgeworfen 5% davon
      5-7,5 mio.

      Was hat die Anlage gekostet, würden diese Kosten abgezogen usw.

      also 5 mio. würden da sicher fällig werden.

      Trading Spotlight

      Anzeige
      InnoCan Pharma
      0,1865EUR 0,00 %
      Multi-Milliarden-Wert in diesem Pennystock?!mehr zur Aktie »
      Avatar
      schrieb am 29.07.14 13:49:12
      Beitrag Nr. 24.056 ()
      Fast 10 Mio sollen sie hinterlegen.... da gehts wohl um mehr als 5 Mio... Im August soll es mit dem Magnetitabbau losgehen... kein Wort dazu. Im Januar waren sie noch kurz davor die Lösung fürs sulfidische Material zu finden... jetzt liest es sich, als wenn noch lange keine Lösung in Sicht wäre... Damit ist auch klar was bei den Q4 Zahlen kommt... eine positive Überraschung sicher nicht...
      Avatar
      schrieb am 29.07.14 14:32:24
      Beitrag Nr. 24.057 ()
      Der Kläger war der

      ehemalige Pächter und Betreiber, der die Selinsing-Goldmine an Monument und

      seine Tochtergesellschaften frei von Belastungen verkaufte. Die Transaktion

      wurde am 25. Juni 2007 abgeschlossen und der Kläger wurde dafür vollständig

      bezahlt. Die Forderung gegen Monument und ihre Tochtergesellschaften

      bezüglich des angeblichen "Joint-Venture-Anteils" des Klägers wurden nicht

      bis zum Jahre 2012 gestellt. Monument bestreitet, dass der Kläger

      irgendeinen "Joint-Venture-Anteil" an der Selinsing-Goldmine besitzt und

      beabsichtigt, diese Forderung weiterhin energisch anzufechten.


      Ich sehe nicht, daß der Kläger Erfolg haben könnte.
      Zum einen wurde wohl ohne Belastungen verkauft -
      und zum anderen scheint die Forderung verjährt zu sein.
      Isi
      1 Antwort?Die Baumansicht ist in diesem Thread nicht möglich.
      Avatar
      schrieb am 29.07.14 14:40:40
      Beitrag Nr. 24.058 ()
      Ja sehe ich auch so 2007 ist schon extrem lange her frage man sich wieso der Kläger so eine Zirkus macht.

      Wahrscheinlich hält Monument Mining deshalb auch alle Bohrergebnisse und Recourenschätzungen zurück um dem Kläger nicht noch mehr Futter zu geben.

      Ist nur doof das die 10 Millionen Dollar auf einem Treuhandkonto gebunden sind.
      Avatar
      schrieb am 29.07.14 14:55:56
      Beitrag Nr. 24.059 ()
      Antwort auf Beitrag Nr.: 47.391.278 von Isengrad am 29.07.14 14:32:24aber irgendwas muss doch dahinter sein sonst hätte der Kläger 2013 nicht Recht bekommen!!!
      Avatar
      schrieb am 29.07.14 15:07:58
      Beitrag Nr. 24.060 ()
      Zitat von Isengrad: und zum anderen scheint die Forderung verjährt zu sein.

      Isi


      1)
      Verjährungsvorschriften dort ?

      2)
      Dürfte auch dort der Ablauf der Verjährung ab Rechtshängigkeit gehemmt sein.

      3)
      Soweit es um Gewinnanteile gehen sollte...die können ja schlecht verjähren, bevor sie überhaupt entstanden sind (2007).
      • 1
      • 2406
      • 2840
       Durchsuchen


      Beitrag zu dieser Diskussion schreiben

      MONUMENT Mining Ltd. (WKN: A0MSJR) Goldproduzent aus Kanada!!!!!!!!!!!!!!!!