checkAd

    `Avino Silver´(ASM.V) besser als `Mines Management´(MGN)? (Seite 59)

    eröffnet am 22.12.04 21:46:10 von
    neuester Beitrag 18.04.24 11:11:06 von
    Beiträge: 1.461
    ID: 938.312
    Aufrufe heute: 0
    Gesamt: 133.313
    Aktive User: 0

    Werte aus der Branche Rohstoffe

    WertpapierKursPerf. %
    0,7750+17,42
    0,7200+12,50
    0,8947+11,85
    205,00+10,81
    5,1500+8,42
    WertpapierKursPerf. %
    6,1500-10,61
    183,20-19,30
    1,1367-22,67
    12,000-25,00
    46,95-98,00

    Beitrag zu dieser Diskussion schreiben

     Durchsuchen
    • 1
    • 59
    • 147

    Begriffe und/oder Benutzer

     

    Top-Postings

     Ja Nein
      Avatar
      schrieb am 02.06.14 00:35:40
      Beitrag Nr. 881 ()
      Antwort auf Beitrag Nr.: 47.078.622 von Fantomas96 am 31.05.14 08:17:27
      Zitat von Fantomas96: - wie sieht das mit den Tailings aus -das sind ja quasi die 500tpd??
      Müsste man natürlich berücksichtigen.
      Neben einigem anderen.
      Verstehe ich nicht. Was haben die Tailings mit 500tpd zu tun ?



      Ich dachte es so verstanden zu haben, beziehungsweise dazu war ich mir genau nicht sicher dass die jetzt bestehende 500tpd Förderung aus den Tailings kommt?

      Gruß
      P.
      5 Antworten
      Avatar
      schrieb am 31.05.14 08:17:27
      Beitrag Nr. 880 ()
      Zitat von Popeye82: Ich habe mal einige naive Anfängerfragen.

      - sind die Erweiterungsarbeiten schon, vollständig, bezahlt?
      Nein, glaube ich nicht. Aber finanziert durch das letzte PP

      Und wenn nicht, wieviel ist etwas noch zu leisten?
      Keine Ahnung

      - muss Avino, nach der Erweiterung, Kredite bedienen(glaube, soweit ich es sehe, nur die Kreditzusage?)?
      Haben nur ne Kreditaufnahme von Caterpillar für Minengeräte über $5 Mio.

      - wie sieht das mit den Tailings aus -das sind ja quasi die 500tpd??
      Müsste man natürlich berücksichtigen.
      Neben einigem anderen.
      Verstehe ich nicht. Was haben die Tailings mit 500tpd zu tun ?

      Und sollte San Gonzalo relativ durchgehend, bis zum Ende, 500tpd hergeben?
      wird ja noch weiter exploriert, von daher ???

      - wenn die Erweiterung abgeschlossen ist, kann man dann -einigermassen berechtigterweise- ein (mindestens)ähnliches Kostenniveau erwarten?
      habe leider keine Glaskugel.

      - wenn der Ausbau abgeschlossen ist, dürfte ja wahrscheinlich in andere/"neue" Projekte investiert werden.
      Lassen sich da irgendwelche groben Kalkulationen machen in welchem Masse das den Cashflow beeinflussen würde?
      lass die erst mal die 1000tpd an den Start bringen und wieder von der Avino Mine fördern. Danach dann vielleicht die Tailings Förderung....
      und daaaaannnn sehen wir weiter



      Grundsätzliche Einschätzung, bisher: das sieht, (vor allem)unter einer Cashflow Perpektive, erstmal interessant aus.
      Gefällt mir, auf Basis der Presentation, erstmal ganz gut.

      Gruß
      P.
      6 Antworten
      Avatar
      schrieb am 31.05.14 01:12:56
      Beitrag Nr. 879 ()
      Antwort auf Beitrag Nr.: 47.066.176 von Fantomas96 am 29.05.14 07:56:51
      Ich habe mal einige naive Anfängerfragen.

      - sind die Erweiterungsarbeiten schon, vollständig, bezahlt?
      Und wenn nicht, wieviel ist etwas noch zu leisten?
      - muss Avino, nach der Erweiterung, Kredite bedienen(glaube, soweit ich es sehe, nur die Kreditzusage?)?
      - wie sieht das mit den Tailings aus -das sind ja quasi die 500tpd??
      Müsste man natürlich berücksichtigen.
      Neben einigem anderen.
      Und sollte San Gonzalo relativ durchgehend, bis zum Ende, 500tpd hergeben?
      - wenn die Erweiterung abgeschlossen ist, kann man dann -einigermassen berechtigterweise- ein (mindestens)ähnliches Kostenniveau erwarten?
      - wenn der Ausbau abgeschlossen ist, dürfte ja wahrscheinlich in andere/"neue" Projekte investiert werden.
      Lassen sich da irgendwelche groben Kalkulationen machen in welchem Masse das den Cashflow beeinflussen würde?


      Grundsätzliche Einschätzung, bisher: das sieht, (vor allem)unter einer Cashflow Perpektive, erstmal interessant aus.
      Gefällt mir, auf Basis der Presentation, erstmal ganz gut.

      Gruß
      P.
      Avatar
      schrieb am 29.05.14 10:23:48
      Beitrag Nr. 878 ()
      Gold auf $865 ? Ja, den Vertreter kenne ich.
      Der ist gerade mal wieder auf Extremaussagen-Modus, will ja dann auch $5000'sehen.

      Nee, für mich ist bei $1150 Schluß nach unten, wenn es ganz extrem kommt dann vielleicht noch kurzfristig an die $1100 ran. Selbst an Gold $1000 glaube ich nicht.

      Sollte Gold nicht kurzfristig absacken und seitwärts in der $1200 - 1300 Range laufen, werde ich spätestens im August wieder stärker einsteigen, ansonsten bei Absacken auf die $1150 - 1100.
      Avatar
      schrieb am 29.05.14 09:04:14
      Beitrag Nr. 877 ()
      Antwort auf Beitrag Nr.: 47.066.176 von Fantomas96 am 29.05.14 07:56:51Moin Fantomas,

      machst Du Deine Nachkäufe eher vom Monat (Juli/Aug) abhängig oder sieht Du bei Gold und Silber "irgendwo" einen Boden?
      Jetzt liest man schon von "bei 865 USD wäre ein guter Boden beim POG", mein Gott.;)

      Schönen Feiertag
      timesystem

      Trading Spotlight

      Anzeige
      InnoCan Pharma
      0,1995EUR +1,01 %
      Wirksames Medikament für Milliarden Patienten?mehr zur Aktie »
      Avatar
      schrieb am 29.05.14 07:56:51
      Beitrag Nr. 876 ()
      Sowohl finanziell wie operativ ein sehr starkes Quartal und man ist voll auf 1,2 Mio. Silberäquivalent- Unzen Kurs für 2014 mit den bestehenden 500tpd (ohne die gerade im Aufbau befindliche 1000tpd Anlage).
      Auch die All-In Sustaining Cash Costs haben sich deutlich auf $12,85 (von $20,60) verringert,

      Ich warte allerdings noch mit dem Nachkauf, da ich in den nächsten Wochen noch mit weiterem Preisverfall bei den Edelmetallkursen rechne. Da kommt vielleicht ein "finaler Abverkauf" bei Edelmetallen und Minern und dann sollte man bei guten Werten zuschlagen (die 3x Bull ETF's NUGT und JNUG sind auch schon wieder nahe der All-Time Lows und damit in interessantem Kaufterritorium).
      Vielleicht so im Juli / August dann eine sehr gute Kaufsituation.
      2 Antworten
      Avatar
      schrieb am 29.05.14 05:33:05
      Beitrag Nr. 875 ()
      ich habe die Aktie nicht.
      Eventuell Erwägung für eine Momentumspekulation.

      Avino Reports 1rst Quarter `14 Financial Results of $1.344.316; $0.05/Share +Cash Flow From Operations of $1.631.349; $0.05/Share; Cash cost per AgEq ounce was $8.62, compared to $14.77 in Q1 `13, Consolidated all-in sustaining cash cost per AgEq ounce was $12.85, compared to $20.60 in Q1 `13, Avino will be holding a conference call on Thursday, May 29, `14 @9 am PST(12 pm EST) - May 28, 2014
      www.stockhouse.com/news/press-releases/2014/05/28/avino-repo…
      Avatar
      schrieb am 23.04.14 16:25:17
      Beitrag Nr. 874 ()
      Antwort auf Beitrag Nr.: 46.860.970 von Fantomas96 am 23.04.14 12:22:30AVINO Expansions Update

      23.April 2014



      http://www.avino.com/s/news.asp?ReportID=648963



      Avino Silver & Gold Mines Ltd. (ASM: NYSE - MKT, ASM: TSX.V; "Avino" or "the Company") is pleased to announce the following expansion update from its Avino Mine located on Avino property located 80km northeast of Durango, Mexico.

      "Having just returned from a week at the mine site, I am extremely pleased with the progress being made at the Avino Mine and the mill complex; with the closing of the two financings in February, we are in great shape to complete our expansion within 2014, as planned."

      - David Wolfin, President, CEO & Director, Avino Silver & Gold Mines Ltd.

      Avino Mine Expansion
      Dewatering (93% Complete)
      The Avino Mine is now dewatered down to level 10.5 with one more level to go before the area where mining ceased in 2001 is reached. At the current dewatering rate, it is anticipated that mining can commence in the 3rd Quarter or possibly sooner pending completion of dewatering.
      Main Haulage Ramp Rehabilitation (85% Complete)
      The ramp in general is in very good condition as the host rock is very competent; areas where sloughing has occurred are being stabilized with steel and timber sets and sprayed with shotcrete. The rehabilitation has kept pace with dewatering so once dewatering in the final level is complete the final rehabilitation will be swift.
      New Underground Mining Equipment (Received)
      New Oldenberg single boom jumbo and Caterpillar RG 1600 six yard scoop tram have been purchased using the Caterpillar credit facility; this equipment is in addition to a scoop tram and air compressor that were previously purchased for the rehabilitation work.
      2 New Portable Mine Offices (Received)
      5 New Personnel Mine Diesel Trucks (Received)
      Process Plant Expansion

      1500 TPD Crushing Area
      New 150 tonne live capacity coarse ore bin has been completed.
      Pioneer 30x42 jaw crusher has been completely rebuilt, tested and installed on its new foundation.
      Feeder from new coarse ore bin to the Pioneer jaw crusher and additional conveyor belts to complete the crushing circuit configuration are currently being installed.
      New scalping screen and product screen have been purchased and awaiting delivery for installation.
      New self-cleaning magnet and metal detector over the existing jaw crusher discharge conveyor have been installed and are in service.
      Grinding Area
      Repairs to the large 11x15 Marcy ball mill in circuit 3 have been completed. Rubber liners will be installed following delivery.
      New pump box and a pair of 8x6 cyclone feed pumps have been installed together with their dedicated classification cyclones.
      A new electrical starter and clutch for the ball mill have been ordered.
      Flotation Area
      Repairs to the existing bank of 3 Outokumpu 3,900 cubic foot flotation cells have been completed. They have been fitted with new mechanisms.
      Related launders and piping for individual concentrates have been routed to their individual pump boxes fitted with vertical 2.5" Galigher pumps.
      New scavenger and cleaner cells have been fabricated using existing available spare parts to complete the flotation section of the mill circuit.
      New blower has been ordered to service the new flotation cells.
      Dewatering Area
      Existing 40 foot water reclaim tank will be used for thickening the concentrate of Circuit 3.
      Currently reviewing and evaluating proposals for the thickener mechanism.
      New concentrate filter press from Bilfinger has been ordered. Delivery from Europe will be in late April/May.
      Engineering of the layout and foundations for the press are presently in progress.
      Infrastructure

      Power Line Construction

      Discussions with CFE, the Mexican electrical utility company, on the new 34.5kv power line have been completed along with the study covering the proposed location of the towers and power poles. Permitting and consultation discussions with the Ejidos have been taking place and the initial feedback has been favorable. Construction of the power line will proceed once permits are in place and any negotiations with the Ejidos affected by the new power line have concluded and permits have been issued. The Company estimates that the power line will be completed in Q4 2014.

      New Tailing Facility

      A study to provide engineering services for the new tailings facility is underway. Condemnation drilling and trenching for test samples has been completed with no significant findings; there was no sign of mineralization in the drill core. This work is expected to take approximately 16 weeks to produce a report in support of our application for a permit to dispose mill tailings in the new storage area. The report will come complete with the dam design, water reclamation system and the amount of fill material required for the capital cost estimate.

      Avino continues to make health and safety a top priority. The Company recently established a new rescue facility for training purposes and outfitted it with new equipment.

      Photographs from management recent trip to the mine are available on Avino's website or by clicking here.

      Avino is very proud of its fleet of mining equipment and processing facility. Since the Company re-commenced operations in 2010, it's goal has been to create a modern and highly efficient operation. We believe that we are reaching our goal by acquiring brand new underground mining equipment which includes the latest technology, such as GPS transmitters, that can send data to centralized computers to generate monthly reports. These reports are used to analyze the status of equipment to mitigate down time and ensure efficient operation. Further, Management can monitor equipment remotely and in real time to take corrective action quickly.

      About Avino

      Avino is a silver and gold producer operating the Avino property located in Durango, Mexico. The Company's mission is to become a mid-tier silver producer through profitable organic growth at the Avino property. We are committed to managing all business activities in an environmentally responsible and cost-effective manner while contributing to the well-being of the community in which we operate.
      Avatar
      schrieb am 23.04.14 12:22:30
      Beitrag Nr. 873 ()
      Antwort auf Beitrag Nr.: 46.846.818 von dosto am 18.04.14 15:28:14Ja, dosto, meine $10/Unze von 02/2013 waren ja auch Cash Costs und damit bei $10,02 doch fast perfekt geschätzt, oder ?

      Wir wissen ja beide, dass sich da einiges in der Berechnung/Angabe in den letzten 12 Monaten getan hat (Stichwort: All-In Sustaining Costs, die allerdings auch nicht standardisiert sind).

      Eingehend auf Deine Berechnung, daher folgende Anmerkungen:

      1. Wenn man nicht mit den PRODUZIERTEN Silber-Äquivalent Unzen (895.240) rechnet, sondern mit den VERKAUFTEN (789.135), dann kommen sogar $ 11,36 Cash Costs pro Äquivalent Unze raus (bei angesetzten Kosten von $8.968.409).
      Allerdings würde ich da Abschreibungen/Wertminderungen ($949.326) wieder abziehen und käme auf Cash (Production) Costs pro Silber-Äquivalent Unze (verkauft) von $10,16.

      2. nur eine kleine Änderung bei den Investing Activities:
      Du bist von $3.315.192 (CapEx) und $901.912 (Exploration & Evaluation) ausgegangen. Allerdings sollte man dann auch Anlageverkäufe ($88.637) berücksichtigen und kommt dann auf:
      CapEx: $3,60
      E&E: $ 1,01
      -> Investing Costs pro Silber-Äquivalent Unze = $ 4,61

      Zu den damit errechneten $ 19,37 pro PRODUZIERTER Unze (zu Deinen $19,47 also nur marginaler Unterschied) könnte man dann noch Financing Costs und Steuern hinzurechnen.
      Dann weiß man auch, warum sich die Cash Situation zum Vorjahr negativ entwickelt hat (von $4,035,985 auf $3,839,595).

      Allerdings sollte man dann auch dazu sagen, dass die CapEx Kosten von $3,31 Mio. (=$3,70 pro Unze) hauptsächlich für die zweite (250 tpd) Verarbeitungsanlage ausgegeben wurden und in dieser Höhe dafür nicht mehr anfallen.

      Das aufgenommene PP Kapital wird jetzt in die 1000 tpd Anlage gesteckt, die in Q4/2014 ans Netz gehen soll und damit die Gesamtkapazität auf 1500tpd VERDREIFACHT wird.

      Fazit: ich bin weiterhin positiv gestimmt, da die Exploration gute Ergebnisse liefert, das Cash sinnvoll in die Anlagenerweiterung investiert wird und die Produktionsergebnisse sich ebenfalls gut entwickeln.
      Für mich eine positive "growth story" auf mittlerweile wieder ansprechendem (Kauf-)Kursniveau mit einer Market Cap von $ 53,5 Mio. bei einer geschätzten 2014 Produktion von 1,2 Mio. Unzen (je nachdem, wann die 1000tpd an den Start gehen evtl. noch mehr).
      1 Antwort
      Avatar
      schrieb am 18.04.14 15:28:14
      Beitrag Nr. 872 ()
      Die mining Kosten sind schon bei

      10,02 Dollar

      aber das wars natürlich nicht.

      G+A 4,74 $
      Explotation 1,01 Dollar
      CaPEX 3,70 $

      irgendwelche Einwände?

      egal, für mich stehen 19,47 $
      2 Antworten
      • 1
      • 59
      • 147
       DurchsuchenBeitrag schreiben


      `Avino Silver´(ASM.V) besser als `Mines Management´(MGN)?