    PERTH, AUSTRALIA / ACCESSWIRE / April 20, 2023 /Delivering reliable production· Delivered quarterly production of 46.8 MMboe (520 Mboe/day), down 9% from Q4 2022 due to planned turnaround and maintenance activities. Full-year production guidance …

    PERTH, AUSTRALIA / ACCESSWIRE / April 20, 2023 /

    Delivering reliable production

    · Delivered quarterly production of 46.8 MMboe (520 Mboe/day), down 9% from Q4 2022 due to planned turnaround and maintenance activities. Full-year production guidance remains unchanged.

    · Delivered sales volume of 50.4 MMboe, down 4% from Q4 2022, primarily due to lower production.

    · Delivered revenue of $4,330 million, down 16% from Q4 2022, due to lower production and lower realised prices.

    · Production, sales volume and revenue increased 122%, 112% and 81% respectively from Q1 2022, driven by the expanded operations portfolio post-merger.

    · Achieved high LNG reliability of 99.9% at Pluto LNG and 98.3% at North West Shelf (NWS) Project.

    · Achieved a portfolio average realised price of $85 per barrel of oil equivalent.

    · Sold 32% of produced LNG at prices linked to gas hub indices.

    Executing major projects

    · The Scarborough and Pluto Train 2 projects in Western Australia are now 30% complete, with manufacturing of the export trunkline 86% complete and first concrete poured for Pluto Train 2.

    · The development drilling program for Sangomar progressed, with ten of 23 wells complete. The Sangomar floating production storage and offloading (FPSO) topsides integration and pre-commissioning works continued in Singapore.

    · Subsequent to the period, Mad Dog Phase 2, in the Gulf of Mexico (GoM), successfully achieved first production and will continue to ramp up through 2023.

    Investing in growth

    · Received competitive tenders for Trion, which are currently being evaluated in support of targeted final investment decision (FID) readiness in 2023.

    · Progressed key project activities for H2OK to support targeted FID readiness in 2023.

    Woodside CEO Meg O'Neill said Woodside delivered outstanding operational performance in the quarter, particularly at Pluto LNG where reliability averaged 99.9%.

    "Our operations teams continued to achieve strong outcomes. Production was 122% higher than the corresponding quarter last year, demonstrating the significant value generated by the merger with BHP's petroleum business.

    "Production and revenue declined from Q4 2022 primarily due to planned turnaround and maintenance activities at Australian assets and lower realised prices.

    "We are making good progress on all major growth projects in Australia and globally. The Scarborough and Pluto Train 2 projects are now 30% complete, with construction of key offshore and onshore infrastructure ramping up. First concrete has now been poured on the Pluto Train 2 site. Engagement with stakeholders and regulators on secondary environmental approvals for offshore execution activities continued.

    Seite 1 von 3



    Accesswire
    0 Follower
    Autor folgen
    Mehr anzeigen
    We’re a newswire service standout and fast becoming an industry disruptor. We provide regional, national and global news to thousands of clients around the world. We’re also leading the way in social engagement, targeting and analytics.
    Mehr anzeigen

    Verfasst von Accesswire
    Woodside Energy Group Ltd Announces First Quarter 2023 Report PERTH, AUSTRALIA / ACCESSWIRE / April 20, 2023 /Delivering reliable production· Delivered quarterly production of 46.8 MMboe (520 Mboe/day), down 9% from Q4 2022 due to planned turnaround and maintenance activities. Full-year production guidance …