     157  0 Kommentare Orezone Reports 2023 Gold Production and Connection of the Bomboré Mine To the National Grid

    VANCOUVER, British Columbia, Jan. 18, 2024 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF) (the “Company” or “Orezone”) is pleased to announce 2023 gold production results and connection of the Bomboré Mine to the national grid.

    Q4 and Full Year 2023 Production Results

    • Gold production totalled 33,916oz during the fourth quarter, and 141,425oz for the full year 2023, achieving annual guidance of 140,000 to 155,000oz.
    • Gold sales during the quarter were 33,782oz at an average realized price of US$1,997/oz, resulting in sales of US$67.5M.
    • For the full year, gold sales totaled 139,696oz at an average realized price of US$1,940/oz, resulting in sales of US$271.0M.

    Patrick Downey, President & CEO stated, “With a strong Q4, the Bomboré mine had a successful first full year of operations and achieved guidance, which is a testament to the hard work and dedication of our operating team. Operational performance was matched by a strong safety record, with no lost-time injuries in 2023.”

    Bomboré Connection to the National Grid

    Mr. Downey continued, “I am also very pleased to report that construction of the Bomboré powerline was completed on-schedule in late December (Photo 1 below). Commissioning and acceptance by the state power provider SONABEL to bring power to site commenced in early January and has now been completed. Process plant energization is in progress and will be completed by January 21, 2024.

    The powerline replaces the use of onsite diesel gensets for power, significantly lowering our operating costs and carbon footprint.”

    Phase II Expansion

    Early works for the Bomboré Phase II expansion commenced in the fourth quarter of 2023. These activities included: ordering of the SAG mill, early-stage engineering, and bulk earthworks (Photo 2 below) on the hard rock mill site.

    Discussions with our senior lender, Coris Bank, are ongoing and the Company expects to receive a financing proposal later in the first quarter.

    Bomboré 2023 Production Results

      Unit Q4-2023 Q3-2023 Q2-2023 Q1-2023 FY-2023
    Ore processed Tonnes 1,449,769 1,453,541 1,400,160 1,445,693 5,749,163
    Ore grade Au g/t 0.82 0.74 0.87 0.96 0.85
    Plant recovery % 88.9 88.8 91.1 92.2 90.4
    Gold produced Au oz 33,916 30,726 35,482 41,301 141,425
    Gold sold Au oz 33,782 29,167 33,608 43,139 139,696

    Completed Powerline and Substation – Photo 1

    Seite 1 von 3


    Diskutieren Sie über die enthaltenen Werte


    globenewswire
    0 Follower
    Autor folgen

    Verfasst von globenewswire
    Orezone Reports 2023 Gold Production and Connection of the Bomboré Mine To the National Grid VANCOUVER, British Columbia, Jan. 18, 2024 (GLOBE NEWSWIRE) - Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF) (the “Company” or “Orezone”) is pleased to announce 2023 gold production results and connection of the Bomboré Mine to the national …