     140  0 Kommentare Maha Energy AB (publ) (“Maha” or the “Company”) Announces revision of 2020 capital program - an operational update, and a question and answer webcast on Monday 23 March - Seite 2

    The contingent Maha-2 well at Tartaruga will now be postponed until 2021. This will reduce the 2020 capital budget by some US$ 8.3 million. A further possible, but unlikely, future reduction is the Tie-2 water injection well (US$ 4.8 million) at the Tie field. These two projects will have no impact on the 2020 production guidance. The Company will continually assess the current market conditions before a final decision is made on a potential postponement of this well.

    Operational Update
    Tartaruga
    The Company has elected to suspend testing of Maha-1 on Tartaruga for several reasons:

    (a) it is becoming increasingly difficult to move specialized stimulation equipment, including explosives, in and out of the Tartaruga location due to reduced Government administrative personnel activity because of the effect of the Coronavirus,
    (b) the remaining testing operations cover previously tested and hydrocarbon bearing zones that will become ‘trapped’ behind pipe due to the current Tartaruga Facility +/- 800 BOPD handling limit,
    (c) it allows the Company to utilize capital more effectively elsewhere in the organization in response to the low oil prices.

    The higher than expected oil rates from the 107D well, which tested at a surface restricted rate of 939 BOPD in February, will more than adequately fill the current production handling capacity at the Tartaruga Facility of approximately 800 BOPD. The Tartaruga facility is currently undergoing an expansion program whereby the facility is upgraded to handle up to 2500 BOPD and 2500 MSCFPD of associated gas. While important subsurface information would be gathered from the well test, little is gained by completing the Maha-1 testing program until such time the Tartaruga Facility is able to handle volumes greater than 800 BOPD.

    Tie Field
    Despite this planned reduction in capital investment, the Company remain focused on the continued production development of the Tie oil field.

    GTE-4
    A workover of the GTE-4 well has commenced and is forecasted to be completed before the end of March. GTE-4 was a dually completed free flowing well that has now reached the normal point of needing artificial lift for flow optimization. This well will now be turned into a pumping well and production is expected to resume to above previous production volumes.

    Tie South-1 (“TS-1”) and Tie South-2 (“TS-2”)
    Final environmental approvals were obtained in February for these two wells. Planning is far advanced, and location preparation work is expected to start in early April. A drilling rig has been located and is currently being contracted. All tangible equipment for these wells has already been purchased. Each well is anticipated to take 40 – 45 days to drill and complete. TS-1 is a near vertical dual producer whilst the TS-2 is planned to be a dual water injector.

    Seite 2 von 3



    globenewswire
    0 Follower
    Autor folgen

    Verfasst von globenewswire
    Maha Energy AB (publ) (“Maha” or the “Company”) Announces revision of 2020 capital program - an operational update, and a question and answer webcast on Monday 23 March - Seite 2 ­­­Maha Energy AB (publ)Strandvägen 5ASE-114 51 Stockholmwww.mahaenergy.ca Press ReleaseStockholmMarch 20, 2020 Maha Energy AB (publ) – Announces revision of 2020 capital program - an operational update, and a question and answer webcast on …