     134  0 Kommentare AS Tallinna Vesi's operational perfomance during 2020

    2020 was an extraordinary year due to the COVID-19 pandemic and caused Tallinna Vesi to make changes in its working arrangements, to ensure the continued safety of staff and uninterrupted services to customers. This ensured we maintained high standards in the quality of both drinking water and final treated effluent, as well as improved network reliability. A number of quality parameters showed a record performance in 2020.

    We ensured high-quality drinking water supply and compliant effluent

    In 2019, the water samples taken from customer’s taps were 99.04% compliant with all quality requirements, in 2020 this same parameter reached 99.71%. This is a result of further investments into the network and enhanced maintenance regimes, which were introduced following the introduction of a more sensitive water quality test into Estonia.

    In order to operate efficiently and use water resources sparingly, we have made great efforts to reduce leakages in the water network. The all-time low record of 12.42% in leakage rate that the Company achieved in 2020, is a testament to that work. The leakage rate for 2019 was 12.97%. The consistent improvement in leakage rates, from the pre-privatisation rate of over 35% in 2000, demonstrates appropriate capital investments into the network and robust repair and maintenance regimes.

    Similar to previous years, the final treated effluent at Paljassaare Wastewater Treatment Plant was compliant with all quality requirements in 2020. In order to further improve the treatment efficiency and final effluent quality, our wastewater laboratory continually analyses samples taken from different stages of the wastewater treatment process.

    Improved reliability of services

    We work hard to limit interruptions in the water network and minimise their duration when they occur. During 2020, the average water disruption time remained stable at 2 hours and 56 minutes per property compared to 2 hours and 59 minutes in 2019.

    The number of sewer blockages and sewer collapses showed a significant improvement in comparison with 2019, reducing by 13% and 22% respectively. A contributing factor to that was the warmer winter that facilitated additional maintenance on the network.

    In 2020, we reconstructed 4.7 km of water pipes and 3.8 km of sewers. During the last five years (2016-2020), the Company has reconstructed a total of 27 km of water pipes and 26 km of sewers.

    In terms of enhancing the reliability of water supply service to customers, the largest project delivered was on Punase Street, where the water main supplying 100,000 residents in Lasnamäe and Maardu, was reconstructed. Another key project related to a section of the water pipe on Järvevana Rd, improving the security of water supply for residents and companies in the Mustamäe and Õismäe districts of Tallinn. Also, the pumping stations on Jääraku Str in Pirita-Kose and on Kolde Blvd in Northern Tallinn received investments related to new technology and telemetry.

    Seite 1 von 3



    globenewswire
    0 Follower
    Autor folgen

    Weitere Artikel des Autors


    Verfasst von globenewswire
    AS Tallinna Vesi's operational perfomance during 2020 2020 was an extraordinary year due to the COVID-19 pandemic and caused Tallinna Vesi to make changes in its working arrangements, to ensure the continued safety of staff and uninterrupted services to customers. This ensured we maintained high …

    Schreibe Deinen Kommentar

    Disclaimer