checkAd

     109  0 Kommentare TeraWulf Updates Mining Operations and Cost-Reduction Initiatives - Seite 2

    The Nautilus Cryptomine facility, which has access to an initial 200 MW of mining capacity from Talen’s 2.3 GW Susquehanna Nuclear Station in Pennsylvania, with an option for an incremental 100 MW, is in the final stages of construction and is projected to begin mining at scale in Q1 2023. Pursuant to the Nautilus JV, TeraWulf owns and is expected to operate 50 MWs of mining capacity at a five-year contracted fixed rate of $0.02 per kilowatt hour, which is among the lowest power pricing in the sector. The Company has received or is awaiting delivery of approximately 15,000 miners (1.7 EH/s) to fill its 50-MW share of the Nautilus Cryptomine facility in Q1 2023. The miners for TeraWulf’s share of the Nautilus Cryptomine have been paid for and the Company does not expect any additional infrastructure related capital expenditures to be required.

    TeraWulf continues to target achieving a total of approximately 6.6 EH/s of operational mining capacity across its two mining facilities in Q1 2023.

    NY Crypto Moratorium Will Not Impact Lake Mariner Facility

    On November 22, 2022, the Governor of the State of New York, Kathy Hochul, signed into law legislation that had been approved earlier this year by the State Assembly, which restricts the issuance of new air permits for proof-of-work mining operations sourcing energy from fossil fueled power plants.

    This bill does not impact operations at TeraWulf’s Lake Mariner Facility in New York as the facility does not source energy directly from a fossil fuel power plant, but rather utilizes >91% sustainable, zero-carbon energy from the grid.

    TeraWulf will continue to expand its sustainable mining footprint at the Lake Mariner facility and partner with the New York Power Authority (NYPA) and other state entities to participate in programs that provide the State’s grid with a significant demand energy response capability.

    Management Commentary

    “We are pleased with the ramp in mining operations achieved at Lake Mariner in a brief period of time and despite the difficult market environment. Given our industry leading low cost of power at our two mining facilities, we believe we are going to be one of the few players that can sustainably operate in a prolonged low-price bitcoin environment,” stated Paul Prager, Co-founder and Chief Executive Officer of TeraWulf. “The recent regulatory actions in New York serve to reinforce our belief that a sustainable, zero-carbon power strategy is critical for long-term success in the bitcoin mining industry, particularly at a time when bitcoin mining and crypto in general have come under greater regulatory scrutiny.”

    Seite 2 von 4


    Diskutieren Sie über die enthaltenen Werte


    Business Wire (engl.)
    0 Follower
    Autor folgen

    TeraWulf Updates Mining Operations and Cost-Reduction Initiatives - Seite 2 TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), which owns and operates vertically integrated, domestic bitcoin mining facilities powered by more than 91% zero-carbon energy, today provided an operational update and more detail regarding …