     384  0 Kommentare Ivanhoe Mines Begins Construction of First Box Cut for Planned Underground Mine at the Kamoa Copper Discovery in the Democratic Republic of Congo - Seite 2

    To view Figures 1 and 2, visit the following link: http://media3.marketwire.com/docs/IVN_figures1and2.pdf

    Underground mining to use mechanized room-and-pillar and drift-and-fill methods

    Given the favourable geological characteristics of the Kamoa Deposit as derived from the December 2012 mineral resource - including its relatively undeformed, continuous mineralization - it is considered amenable to large-scale, mechanized, room-and-pillar and drift-and-fill mining. The overall dip and geometry of the resource make it conducive to room-and-pillar mining in the shallow portions of the deposit, which will transition to drift-and-fill mining in the deeper or steeper sections. These methods are the accepted industry standards for mining deposits such as Kamoa.

    Infill drilling of the planned initial mining area from the PEA has confirmed the overall grade and thickness of the December 2012 resource estimate in these areas and provided invaluable refinement within localized areas. While traditionally modelled on a 1% total copper cut-off to define a selective mineralized zone (SMZ), the deposit has shown that grade continuity also exists at an elevated 1.5% total copper vertical cut-off, and that a 2.0% total copper vertical cut-off may be feasible in certain areas. Applying higher cut-offs in defining the SMZ will allow for implementation of higher-grade, narrower mining options which should improve overall mine economics. Defining the SMZ at higher vertical cut-offs also has created more expansive, contiguous zones of high-grade mineralization.

    Progress on pre-feasibility study, with initial development planned at Kansoko Sud

    In line with the phased approach to project development outlined in the 2013 updated Kamoa PEA, the Kamoa pre-feasibility study (PFS) is progressing on the basis of an initial three-million-tonne-per-annum (3 Mtpa) mine and concentrator. Development plans will be refined following completion of the PFS.

    Reviews of the resource model, combined with results from recent infill drilling at Kansoko Sud, have confirmed grade continuity, which allows the resource model to be constrained at a higher cut-off grade. The focus in planning the early years of mine production continues to be on the near-surface and high-grade material from Kansoko Sud to maximize margins. The 3 Mtpa mine and concentrator can be split into modules to potentially better match the underground ramp-up and further reduce the pre-production development capital. This will be examined in more detail as part of the pre-feasibility study to provide flexibility to the development of the Kamoa Project.

    Seite 2 von 4



    Verfasst von Marketwired
    Ivanhoe Mines Begins Construction of First Box Cut for Planned Underground Mine at the Kamoa Copper Discovery in the Democratic Republic of Congo - Seite 2 LUBUMBASHI, DEMOCRATIC REPUBLIC OF CONGO--(Marketwired - July 24, 2014) - Ivanhoe Mines (TSX:IVN) Executive Chairman Robert Friedland and Chief Executive Officer Lars-Eric Johansson today announced the start of construction on the box cut for the …