Roxgold Drills 38.3 g/t Au Over 12m, 28.3 g/t Au Over 16m in Koula Deposit as Séguéla Advances Toward Goal of Initial Production Next Year - Seite 3
Figure 2. Koula assay results and assay status
Figure 3: Coarse gold in SGRC1083
(Note: 1m at 289.0 g/t from 83m, core length in image =12cm)
Highlights from the most recent phase of the Indicated infill drilling program at Koula include:
- 12 metres (“m”) at 38.3 grams per tonne gold (“g/t Au”) in drill hole SGRD1065 from 180m including
- 4m at 104.4 g/t Au from 181m
- 16m at 28.3 g/t Au in drill hole SGRD1083 from 77m including
- 2m at 159.6 g/t Au from 83m
- 15m at 24.0 g/t Au in drill hole SGRC1025 from 42m including
- 3m at 95.7 g/t Au from 47m
- 9m at 30.5 g/t Au in drill hole SGRD1064 from 124m including
- 5m at 52.2 g/t Au from 124m
- 13m at 15.1 g/t Au in drill hole SGRD1032 from 189m including
- 3m at 42.7 g/t Au from 195m
- 11m at 13.9 g/t Au in drill hole SGRD1066 from 203m including
- 4m at 12.7 g/t Au from 205m and
- 1m at 72.3 g/t Au from 213m
- 5m at 19.1 g/t Au in drill hole SGRD1070 from 110m including
- 2m at 45.5 g/t Au from 112m
- 13m at 7.3 g/t Au in drill hole SGRD1034 from 108m including
- 2m at 30.7 g/t Au from 108m
- 10m at 9.4 g/t Au in drill hole SGRD1086 from 44m including
- 2m at 31.3 g/t Au from 47m
- 11m at 6.4 g/t Au in drill hole SGRD1029 from 34m including
- 2m at 14.4 g/t Au from 37m
- 11m at 5.6 g/t Au in drill hole SGRD1033 from 158m
- 19m at 3.9 g/t Au in drill hole SGRD1039 from 162m
- 12m at 5.3 g/t Au in drill hole SGRD1073 from 188m
Click here to view the full listing of drill results from the recent drilling programs at the Séguéla Gold Project. Note: all results are reported as down-hole intervals which represent approximately 60% of true width.
Lesen Sie auch
Catalysts and Next Steps
Event |
Timing |
Ongoing infill, expansion and satellite target drilling program at Séguéla |
Q1 2021 |
District exploration drill results at Yaramoko |
Q1 2021 |
Underground drilling program in 55 Zone at Yaramoko Mine Complex |
Q2 2021 |
Boussoura exploration results |
Q2 2021 |
Feasibility Study for Séguéla |