checkAd

     118  0 Kommentare Iris Energy Executes Transformational 600MW Connection Agreement With AEP Texas, Increasing Power Capacity to 765MW (~22 EH/s¹). US$19m Security Deposit and Connection Fee Paid, Procurement and Construction Activities Underway. - Seite 3

    • Focus on low-cost renewables: Iris Energy targets entry into regions where there are low-cost, abundant and attractive renewable energy sources, and where the Company can support local communities
    • Long-term security over infrastructure, land and power supply: Iris Energy owns its electrical infrastructure and data centers, providing security and operational control over its assets. Iris Energy also focuses on grid-connected power access which helps to ensure it is able to utilize a reliable, long-term supply of power
    • Seasoned management team: Iris Energy’s team has an impressive track record of success across energy, infrastructure, renewables, finance, digital assets and data centers

    Forward Looking Statements

    This release includes “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995. Forward-looking statements generally relate to future events or Iris Energy’s future financial or operating performance. For example, forward-looking statements include but are not limited to the expected increase in the Company’s power capacity and the Company’s business plan. In some cases, you can identify forward-looking statements by terminology such as “anticipate,” “believe,” “may,” “can,” “should,” “could,” “might,” “plan,” “possible,” “project,” “strive,” “budget,” “forecast,” “expect,” “intend,” “will,” “estimate,” “predict,” “potential,” “continue,” “scheduled” or the negatives of these terms or variations of them or similar terminology, but the absence of these words does not mean that statement is not forward-looking. Such forward-looking statements are subject to risks, uncertainties, and other factors which could cause actual results to differ materially from those expressed or implied by such forward looking statements. In addition, any statements or information that refer to expectations, beliefs, plans, projections, objectives, performance or other characterizations of future events or circumstances, including any underlying assumptions, are forward-looking.

    These forward-looking statements are based on management’s current expectations and beliefs. These statements are neither promises nor guarantees, but involve known and unknown risks, uncertainties and other important factors that may cause Iris Energy’s actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements, including, but not limited to: Iris Energy’s limited operating history with operating losses; electricity outage, limitation of electricity supply or increase in electricity costs; long term outage or limitation of the internet connection at Iris Energy’s sites; Iris Energy’s evolving business model and strategy; Iris Energy’s ability to successfully manage its growth; Iris Energy’s ability to raise additional capital; competition; bitcoin prices; risks related to health pandemics including those of COVID-19; changes in regulation of digital assets; and other important factors discussed under the caption “Risk Factors” in Iris Energy’s final prospectus filed pursuant to Rule 424(b)(4) with the SEC on November 18, 2021, as such factors may be updated from time to time in its other filings with the SEC, accessible on the SEC’s website at www.sec.gov and the Investors Relations section of Iris Energy’s website at https://investors.irisenergy.co.

    Seite 3 von 4



    Diskutieren Sie über die enthaltenen Werte



    globenewswire
    0 Follower
    Autor folgen

    Verfasst von globenewswire
    1 im Artikel enthaltener WertIm Artikel enthaltene Werte
    Iris Energy Executes Transformational 600MW Connection Agreement With AEP Texas, Increasing Power Capacity to 765MW (~22 EH/s¹). US$19m Security Deposit and Connection Fee Paid, Procurement and Construction Activities Underway. - Seite 3 Highlights 600MW binding connection agreement executed with AEP Texas and $19m security deposit and connection fee paidPower capacity expected to increase from 165MW (4.6 EH/s) to 765MW (~22 EH/s1) 15.2 EH/s (~530MW) of miners previously secured; …