checkAd

     237  0 Kommentare Perseus Pours First Gold at Yaouré Five Weeks Ahead of Schedule

    PERTH, Western Australia, Dec. 17, 2020 (GLOBE NEWSWIRE) -- Perseus Mining Limited (“Perseus” or the “Company”) (TSX & ASX: PRU) is pleased to advise it has successfully completed the first pour of gold at its Yaouré Gold Mine in Côte d’Ivoire. Perseus achieved this important milestone nearly five weeks ahead of schedule, consistent with its “stretch target” of first gold at Yaouré in December 2020.

    With construction of the Yaouré processing plant and associated infrastructure largely complete, Perseus will now focus on satisfying continuous performance tests and positioning to declare Commercial Production. Perseus expects to achieve both during the March 2021 quarter, when the first shipment of gold from the Yaouré mine site is also expected to occur.

    Perseus acquired Yaouré when it merged with Amara Mining plc in April 2016. Since then, the Company has completed an extensive programme of confirmatory drilling and test work and prepared a definitive feasibility study (DFS). After permitting and negotiating a Mining Convention with the Ivorian government, construction of the US$265 million mine started in August 2019.

    Initially, lower grade oxide ore mainly from decommissioned heap leach pads will be processed in the Yaouré plant pending access to higher grade fresh ore from the CMA pit. During the first five years of the Yaouré mine life, our DFS forecasts annual gold production averaging around 215,000 ounces at a weighted average all in site cost of (AISC) of approximately US$750 per ounce. An updated Life of Mine Plan for Yaouré, taking the actual commissioning date, current mining rates, operating costs and possible increases in Mineral Resources into account, is scheduled for release in the March 2021 quarter.

    With the successful development and commissioning of Yaouré, Perseus will own and operate three gold mines (Edikan, Sissingué and Yaouré) in two West African countries (Ghana and Côte d’Ivoire) and will be on track to achieve its goal to produce more than 500,000 ounces of gold per year at a cash margin of more than US$400 per ounce, and become a reliable intermediate gold company that generates material benefits for all of its stakeholders.

    Perseus’s Managing Director & Chief Executive Officer, Mr Jeff Quartermaine said:

    “Pouring our first gold at Yaouré yesterday represented the achievement of a major milestone in the construction and commissioning of Perseus’s third gold mine. It also represented the delivery of another promise made to shareholders by Perseus’s management team, namely, to achieve its stretch target of first gold at Yaouré in December 2020. 
    Seite 1 von 4


    Diskutieren Sie über die enthaltenen Werte


    globenewswire
    0 Follower
    Autor folgen

    Verfasst von globenewswire
    Perseus Pours First Gold at Yaouré Five Weeks Ahead of Schedule PERTH, Western Australia, Dec. 17, 2020 (GLOBE NEWSWIRE) - Perseus Mining Limited (“Perseus” or the “Company”) (TSX & ASX: PRU) is pleased to advise it has successfully completed the first pour of gold at its Yaouré Gold Mine in Côte d’Ivoire. …