    MMB has reported to Baja that it has completed its most recent schedule review for the Boleo Project, and has advised the Company of the following:

    • Piping and instrumentation construction schedules remain under pressure due to ongoing work force shortages;
    • MMB is now targeting mechanical completion of the copper circuit by the end of June 2014. First ore or hot commissioning is now expected to commence in early September, with October 1, 2014 being the targeted date for first copper production; and
    • Mechanical completion of the cobalt zinc circuits is now scheduled for the middle of August 2014 due to lateness in delivery of certain equipment. Additionally, delays to the completion of the copper circuit are having a knock-on effect preventing the movement of crews to work on the construction of the back-end. First cobalt zinc production is now scheduled for November 1, 2014.

    Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

    Lesen Sie auch

    CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS: This press release contains forward-looking statements or forward-looking information (forward-looking statements). These statements can be identified by expressions of belief, expectation or intention, as well as those statements that are not historical fact. Forward-looking statements involve a number of risks, uncertainties and assumptions that could cause actual results or events to differ materially from those expressed or implied by the forward-looking statements. Forward-looking statements contained in this press release are based on our current estimates, expectations and projections, which the Company believes are reasonable as of the current date. Actual results could differ materially from those anticipated or implied in the forward-looking statements and as a result undue reliance should not be placed on forward-looking statements. Additional risks and uncertainties can be found in the Company's reporting documents filed on SEDAR (www.sedar.com), including its Management Discussion and Analysis and Annual Information Form. Forward-looking statements are given only as at the date of this press release and the Company disclaims any obligation to update or revise the forward-looking statements, whether as a result of new information, future events or otherwise, except as required by law.

    Baja Mining Corp.
    Tom Ogryzlo
    Interim CEO
    604-685-2323
    604-629-5229 (FAX)
    info@bajamining.com
    www.bajamining.com
    Seite 2 von 2




    Verfasst von Marketwired
    Baja Issues Corporate Update and Provides Boleo Start-up Schedule Update - Seite 2 VANCOUVER, BRITISH COLUMBIA--(Marketwired - June 23, 2014) - Baja Mining Corp. ("Baja" or the "Company") (TSX VENTURE:BAJ)(OTCQB:BAJFF) is pleased to announce that further to its news release of May 13, 2014, Minera y Metalúrgica del Boleo, S.A. …