     136  0 Kommentare Maxim Power Corp. Reports Fire Incident at Milner 2

    CALGARY, Alberta, Oct. 02, 2022 (GLOBE NEWSWIRE) -- Maxim Power Corp. ("MAXIM" or the "Corporation") (TSX: MXG) responded to a fire at its 204 MW Milner 2 (“M2”) facility located near Grande Cache, Alberta.

    During the afternoon of September 30, 2022, a fire occurred at the M2 facility. Emergency crews were dispatched and quickly extinguished the fire. MAXIM holds safety as its highest priority for its people, community and emergency responders and reports that all personnel involved in the incident are safe. The appropriate authorities have been informed and an investigation as to the cause of the fire and extent of the damage is currently underway. MAXIM is also in the process of evaluating an insurance claim for damages and future lost earnings.

    As previously reported, the M2 facility has been offline since early September for cold commissioning activities related to the Combined Cycle Gas Turbine (“CCGT”) expansion of M2. As a result of this incident, MAXIM anticipates that the timing of the hot commissioning activities and the commercial operations date, of the CCGT expansion of M2, will be impacted. Damages could cause a significant delay to the commissioning and operations of the CCGT expansion of M2. MAXIM does not currently have any forward financial or physical Alberta power positions in place and its forward financial natural gas long position does not extend beyond the current month. Further information will be provided as it becomes available.

    About MAXIM

    Based in Calgary, Alberta, MAXIM is one of Canada’s largest truly independent power producers. MAXIM is now focused entirely on power projects in Alberta. Its core asset – the 204 MW H.R. Milner Plant, M2, in Grande Cache, AB – is a state-of-the-art natural gas-fired power plant that commissioned in Q2, 2020. MAXIM is currently increasing the capacity of M2 to approximately 300 MW and concurrently will realize an improvement in the efficiency of the plant by investing in heat recovery combined cycle technology. In addition, MAXIM continues to explore additional development options in Alberta including its currently permitted gas-fired generation projects and the permitting of its wind power generation project. MAXIM trades on the TSX under the symbol “MXG”. For more information about MAXIM, visit our website at www.maximpowercorp.com. For further information please contact:

    Seite 1 von 2



    globenewswire
    0 Follower
    Autor folgen
    Verfasst von globenewswire
    Maxim Power Corp. Reports Fire Incident at Milner 2 CALGARY, Alberta, Oct. 02, 2022 (GLOBE NEWSWIRE) - Maxim Power Corp. ("MAXIM" or the "Corporation") (TSX: MXG) responded to a fire at its 204 MW Milner 2 (“M2”) facility located near Grande Cache, Alberta. During the afternoon of September 30, …