    Results from the program confirmed the style and grade distribution of the gold mineralization in the area being tested, and included the intersection of high grade and visible gold.

    The program drilled an area of roughly 200 vertical meters over a strike length of 250 meters at 7.5 to 10-meter centers. A total of 63,444 meters was drilled in 364 drill holes and returned 49 intersections grading greater than 1,000 grams of gold per tonne, including the bonanza-grade intercept in hole VU-722 which encountered 37,117 grams of gold per tonne uncut over 0.5 meters.

    Valley of the Kings Mineral Resource Estimate Update

    As a result of the 2015/2016 underground infill drill program, the Valley of the Kings Mineral Resource estimate was updated (see news release dated July 21, 2016). Measured Mineral Resources in the Valley of the Kings increased by 58% to 1.9 million ounces (3.5 million tonnes grading 17.0 grams per tonne gold) and Measured and Indicated Mineral Resources in the Valley of the Kings now total 9.1 million ounces of gold (16.4 million tonnes grading 17.2 grams per tonne gold), an increase from the December 2013 Valley of the Kings Mineral Resource estimate of Measured and Indicated Mineral Resources which totalled 8.7 million ounces of gold (15.3 million tonnes grading 17.6 grams per tonne gold).

    In summary, the updated Mineral Resource estimate has confirmed the geological model for the Valley of the Kings, and combined Measured and Indicated Resources have not materially changed. The Valley of the Kings remains open to the east and west along strike, and at depth.

    The Valley of the Kings Mineral Resource estimate was prepared by Pretivm under the guidance and supervision of Ivor W.O. Jones, M.Sc., FAusIMM, CPgeo who is the independent Qualified Person responsible for the Mineral Resource for the Brucejack Project. Pretivm employed the same approach and methodology as was used for the December 2013 Valley of the Kings Mineral Resource estimate. For details see Brucejack Project Mineral Resources Update Technical Report effective date 19 December 2013.

    2016 Exploration Program

    A grass-roots exploration program in an area east of the Brucejack Project has commenced with two drills on site following up on the 2015 grass-roots exploration program. Results from the program are expected later this quarter.

    Mine Plan Update

    With the completion of the updated Mineral Resource estimate for the Valley of the Kings and success in increasing confidence in the estimate in the areas to be mined in the first three years, the Valley of the Kings mine plan will now be updated in preparation for production development expected to commence later this year.

    Seite 3 von 5




    Verfasst von Marketwired
    Pretivm Reports Second Quarter 2016 Results - Seite 3 VANCOUVER, BRITISH COLUMBIA--(Marketwired - Aug. 10, 2016) - Pretium Resources Inc. (TSX:PVG)(NYSE:PVG) ("Pretivm" or the "Company") is pleased to report the following highlights from the second quarter of 2016 and updates for its high-grade gold …