    Transmission Line

    The transmission line contractor has mobilized to site and has commenced civil work preparation. The towers have begun arriving from the fabricator and installation will be ongoing throughout the spring and summer, with connection to the BC Hydro power grid expected in the fourth quarter.

    To view updated photos of the construction progress please see the following link to the Brucejack construction photo gallery on our website: www.pretivm.com/photo.

    Ian I. Chang, M.A.Sc., P.Eng., Vice President, Project Development, Pretium Resources Inc. is the Qualified Person ("QP") responsible for Brucejack Project development.

    About Pretivm

    Pretivm is constructing a high-grade underground gold mine at its Brucejack Project in northern British Columbia with commercial production targeted for 2017.

    (SEDAR filings: Pretium Resources Inc.)

    Forward-Looking Statements

    This News Release contains "forward-looking information" and "forward looking statements" within the meaning of applicable Canadian and United States securities legislation. Statements contained herein that are not based on historical or current fact, including without limitation statements containing the words "anticipates," "believes," "may," "continues," "estimates," "expects," and "will" and words of similar import, constitute "forward-looking statements" within the meaning of the U.S. Private Securities Litigation Reform Act of 1995. Forward-looking information may include, but is not limited to, information with respect to our planned exploration and development activities, the accuracy of our mineral resource estimates; capital and operating cost estimates; production and processing estimates; the results, the adequacy of Pretivm's financial resources, the estimation of mineral reserves and resources including the 2013 Valley of the Kings Mineral Resource estimate and the Brucejack Mineral Reserve estimate, realization of mineral reserve and resource estimates and timing of development of Pretivm's Brucejack Project, costs and timing of future exploration, results of future exploration and drilling, production and processing estimates, capital and operating cost estimates, timelines and similar statements relating to the economic viability of the Brucejack Project, timing and receipt of approvals, consents and permits under applicable legislation, Pretivm's executive compensation approach and practice, and adequacy of financial resources. Wherever possible, words such as "plans", "expects", "projects", "assumes", "budget", "strategy", "scheduled", "estimates", "forecasts", "anticipates", "believes", "intends", "targets" and similar expressions or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative forms of any of these terms and similar expressions, have been used to identify forward-looking statements and information. Statements concerning mineral reserve and resource estimates may also be deemed to constitute forward-looking information to the extent that they involve estimates of the mineralization that will be encountered if the property is developed. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be forward-looking information.

    Seite 2 von 3




    Verfasst von Marketwired
    Pretium Resources Inc. Brucejack Project Construction Update - Seite 2 VANCOUVER, BRITISH COLUMBIA--(Marketwired - April 18, 2016) - Pretium Resources Inc. (TSX:PVG)(NYSE:PVG) ("Pretivm" or the "Company") is pleased to report on the progress of site construction activities at its high-grade gold Brucejack Project …