    Civil Foundation Work: 75% of the earthworks have been completed for the plant foundations, and final excavations will be conducted once civil drawings have been issued for construction. Civil foundation work is expected to commence in early November, starting with the construction of the retaining wall extension, and followed by civil works in the flotation area, concentrate and water recovery thickeners and the filter press building. At the same time the foundations will be constructed for the new warehouse, reagents mixing and air services buildings.

    Transition to Flotation

    The production of flotation concentrate is expected to commence in July 2022 as soon as all of the flotation cells, concentrate thickener and filter press have been commissioned. In the current production schedule the CIL plant will continue operation until commissioning of the flotation plant commences. We will keep the production going as long as possible to generate cash flow primarily from Selinsing, Buffalo Reef pits and the Peranggih Prospect, provided that readers shall understand that there might be an interruption to production due to the Covid pandemic, and there might be volatility of production in transition to the new life of mine from the existing remaining life of mine.

    During the period from late August to the beginning of October, while the CIL plant has continued operation throughout the time, the elution heat exchanger however has been offline after 10 years’ of service, and the spare was unexpectedly found to have failed. Gold pours were put on hold until October when the unit was re-built and back in service. A suitable replacement heat exchanger has been located in Kuala Lumpur and an order has been placed to secure this unit and delivery is awaited. The Company keeps its repair and maintenance program going to ensure sustained production as planned.

    About Monument

    Lesen Sie auch

    Monument Mining Limited (TSX-V: MMY, FSE:D7Q1) is an established Canadian gold producer that owns and operates the Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is also advancing the Murchison Gold Projects comprising Burnakura, Gabanintha and Tuckanarra (20% interest) in the Murchison area of Western Australia. The Company employs approximately 200 people in both regions and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.

    Seite 3 von 5


    Diskutieren Sie über die enthaltenen Werte


    globenewswire
    0 Follower
    Autor folgen

    Verfasst von globenewswire
    Monument Progresses Flotation Plant Construction at the Selinsing Gold Mine in Malaysia - Seite 3 VANCOUVER, British Columbia, Oct. 14, 2021 (GLOBE NEWSWIRE) - Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or the "Company") is pleased to announce the progress on flotation plant construction at the Selinsing Gold Mine in …

    Schreibe Deinen Kommentar

    Disclaimer