checkAd

    New Gold, dank Merger mit sehr großer Zukunft! (Seite 17)

    eröffnet am 01.04.08 13:40:03 von
    neuester Beitrag 12.02.24 21:03:43 von
    Beiträge: 555
    ID: 1.140.021
    Aufrufe heute: 1
    Gesamt: 71.613
    Aktive User: 0

    ISIN: CA6445351068 · WKN: A0ERPH · Symbol: NGD
    2,5300
     
    CAD
    +1,61 %
    +0,0400 CAD
    Letzter Kurs 29.04.24 Toronto

    Werte aus der Branche Rohstoffe

    WertpapierKursPerf. %
    1,4700+28,95
    1,3200+17,86
    1,0100+13,48
    0,5650+13,00
    0,8400+12,75
    WertpapierKursPerf. %
    0,7100-7,79
    3,3200-9,78
    3,9600-15,74
    12,000-25,00
    46,95-98,00

    Beitrag zu dieser Diskussion schreiben

     Durchsuchen
    • 1
    • 17
    • 56

    Begriffe und/oder Benutzer

     

    Top-Postings

     Ja Nein
      Avatar
      schrieb am 30.03.17 17:19:51
      Beitrag Nr. 395 ()
      Avatar
      schrieb am 14.03.17 18:50:10
      Beitrag Nr. 394 ()
      Antwort auf Beitrag Nr.: 54.338.008 von NickelChrome am 16.02.17 16:47:18Und für 2,50 Euro wieder zurück gekauft. :kiss:
      5 Antworten
      Avatar
      schrieb am 09.03.17 16:58:15
      Beitrag Nr. 393 ()
      Wie versteht ihr die Unternehmens meldung von heute bzgl. des Bought Deal? Ist das ein zweiter Bought Deal oder ist das der vom Februar?
      Avatar
      schrieb am 16.02.17 16:47:18
      Beitrag Nr. 392 ()
      Antwort auf Beitrag Nr.: 54.334.912 von reini81 am 16.02.17 11:30:04Wie cool! Ich habe 1 / 3 meiner Stücke für 3 Euro verkauft...Zu Börsenbeginn wieder heftige Kursausschläge.
      Kurze Spitze bis 3,25 $ nach Eröffnung und Zack geht es wieder runter..
      6 Antworten
      Avatar
      schrieb am 16.02.17 11:30:04
      Beitrag Nr. 391 ()
      ...sieht nicht so schlecht aus!;)

      New Gold Announces 2016 Financial Results with Record Low Costs Driving Strong Margins and Cash Flow

      http://www.newgold.com/investors/NewGoldNews/PressReleaseDet…" target="_blank" rel="nofollow ugc noopener">
      http://www.newgold.com/investors/NewGoldNews/PressReleaseDet…


      Ausschnitte:

      RAINY RIVER – 2016 KEY HIGHLIGHTS
      Project spending during the fourth quarter totalled $146 million, bringing 2016 full-year capital spending at the project to $465 million
      Concrete placement, steelwork erection and cladding complete
      SAG and ball mill shells in place
      Pre-leach thickener tank and leach tanks complete
      Power line completed and main substation has been energized
      Installation of mechanical, piping, electrical and instrumentation in processing facilities over 65% complete through mid-February 2017
      Primary crusher and conveyor system over 80% complete



      Mining activities at Rainy River have progressed well to start 2017. From the beginning of the year through the end of last week the company mined over 4 million tonnes of overburden and waste from the pit which was slightly ahead of the tonnage targeted in New Gold's updated plan announced on January 30, 2017. At the same time, approximately 350,000m3 of construction material has been placed at the starter tailings cell which is also slightly ahead of plan. The contractor that will mine the peat and basal till layers within the pit using smaller equipment has been mobilized and is scheduled to begin work in the pit tomorrow, which should result in increased daily mining rates by New Gold's team in the coming weeks. The September start-up is based on an expectation that the mining rate will continue to increase to an average of approximately 120,000 tonnes per day over the next six months, which includes both planned productivity gains and the impact of changing weather conditions through the spring.

      All of the key structural components of the process facilities have been completed and the setting of mechanical equipment and installation of piping, electrical and instrumentation services is well advanced. New Gold plans to complete the testing of the various components of the process facility using a staged approach, after which the company will complete dry and wet commissioning of the full process circuit.

      The primary crusher and conveyor system are over 80% complete and commissioning of the crusher is scheduled to commence in March of 2017. Thereafter, the commissioning of the ball and SAG mills should start during the second quarter. Finally, the refining portion of the circuit should be completed and ready to begin commissioning early in the third quarter. Dry and wet commissioning of the full process circuit is scheduled to take place in August, which should leave approximately one month before targeted first production for any required adjustments to the circuit.

      The company continues to work closely with Environment and Climate Change Canada towards obtaining an amendment to Schedule 2 of the Metal Mining Effluent Regulations, required to close two small creeks and deposit tailings, which is targeted to be received in the third quarter of 2017. However, as previously disclosed, New Gold's redesign of the tailings management facility incorporated a starter tailings cell within the broader facility that does not require a Schedule 2 amendment from the Federal government. The inclusion of a starter cell is an approach that has been used at other Canadian mining operations. Based on its location and scale, the starter cell would provide capacity for approximately six months of tailings. Once the Schedule 2 amendment is received, New Gold would need approximately three months, in good construction weather, to complete construction of the tailings dam.

      Based on the company's targeted September production start, New Gold expects total 2017 production at Rainy River to be 50,000 to 60,000 ounces. Approximately 15,000 ounces are planned for the pre-commercial production period with revenue for this production being credited against the development capital estimate.

      Over Rainy River's targeted two months of commercial production in 2017, the operating expense is expected to be $905 to $945 per gold ounce with all-in sustaining costs expected to be $1,200 to $1,240 per ounce. Both the operating expense and all-in sustaining costs are well above the levels targeted once Rainy River reaches full capacity. The 2017 costs are negatively impacted by lower gold sales resulting from the combination of throughput being lower than design during commissioning and ramp-up and planned lower grade to be processed during the commissioning phase. In addition, there is approximately $12 million, or $305 per ounce, of sustaining costs budgeted during the commercial production period.

      Project spending at Rainy River during the fourth quarter totalled $146 million, bringing 2016 full-year capital spending at the project to $465 million. The total Rainy River project development capital spending through the end of 2016 was $777 million.

      Based on a C$1.30/US$ exchange rate, the remaining capital cost from the beginning of 2017 to the targeted November commercial production is estimated to be approximately $515 million, inclusive of $40 million of contingency.

      Though the Rainy River construction has presented challenges, New Gold continues to look forward to the expected growth in the company's production and cash flow once Rainy River transitions into operation later this year. Rainy River has multiple important asset qualities including its great jurisdiction, significant annual production potential, long estimated reserve life and continued exploration potential.

      FINANCIAL UPDATE

      New Gold's 2016 year-end cash and cash equivalents were $186 million. During the fourth quarter, the company received the remaining $75 million of the stream deposit from RGLD Gold AG, a wholly-owned subsidiary of Royal Gold Inc. and drew $100 million from its $400 million revolving credit facility. At December 31, 2016, an additional $122 million of the facility was used to issue letters of credit for closure obligations at the company's producing mines and development projects, leaving $178 million undrawn.

      In addition, on February 8, 2017, New Gold announced that the company has entered into a binding letter agreement with Goldcorp Inc. to the sell the company's gold stream on the El Morro project for $65 million cash. Including the El Morro proceeds, the company's pro forma liquidity totals $429 million (cash, undrawn credit facility and El Morro proceeds) plus its expected free cash flow generation from its operating mines in 2017.


      Gruß
      reini81
      7 Antworten

      Trading Spotlight

      Anzeige
      InnoCan Pharma
      0,1975EUR +3,95 %
      InnoCan Pharma: Erwächst aus der LPT-Therapie ein Multi-Milliardenwert?mehr zur Aktie »
      Avatar
      schrieb am 13.02.17 22:00:17
      Beitrag Nr. 390 ()
      Antwort auf Beitrag Nr.: 54.309.728 von rolleg am 13.02.17 18:48:03400 KOZ ? KGV von 4? Alles easy und so Himmelblau... Das ist ja wohl kompletter Müll
      Avatar
      schrieb am 13.02.17 18:48:03
      Beitrag Nr. 389 ()
      New Gold—A Gift from the Gold gods
      http://www.goldinvestmentletter.com/blog/
      1 Antwort
      Avatar
      schrieb am 10.02.17 18:19:11
      Beitrag Nr. 388 ()
      Antwort auf Beitrag Nr.: 54.274.295 von reini81 am 08.02.17 19:53:14Man hat den Eindruck erweckt, dass man ohne Kapitalerhöhung durch kommt.
      Versuche gerade meine Stücke via Börse zu reduzieren. :laugh:
      Avatar
      schrieb am 08.02.17 19:53:14
      Beitrag Nr. 387 ()
      Antwort auf Beitrag Nr.: 54.272.342 von NickelChrome am 08.02.17 16:56:51Hallo,

      wie soll ich das verstehen??

      Gruß
      reini81
      1 Antwort
      Avatar
      schrieb am 08.02.17 16:56:51
      Beitrag Nr. 386 ()
      Antwort auf Beitrag Nr.: 54.271.004 von reini81 am 08.02.17 15:15:24Nun das beflügelt doch das Papier ungemein:laugh::laugh::laugh::laugh: 3.05 +0.22 (7.77%) NGD an NYSE
      2 Antworten
      • 1
      • 17
      • 56
       DurchsuchenBeitrag schreiben


      New Gold, dank Merger mit sehr großer Zukunft!