     129  0 Kommentare Yamana Gold Receives Permit at Jacobina, Initiating Ramp Up of Phase 2 Expansion, Expects Fourth Quarter Company Wide Production to Exceed 270,000 GEO With Costs Tracking to Be the Lowest of the Year - Seite 2

    The ramp up to 8,500 tpd will be achieved through a continuation of incremental improvements to de-bottleneck the processing plant. Optimization of the crushing circuit which did not require the installation of new equipment is already complete. During the first half of 2022 several additional initiatives are expected to be complete including optimizing the grinding process with the installation of ultrasonic density meters to optimize ore feed control to the mills and increasing the capacity of the electro-winning circuit. In 2023, further initiatives could be undertaken to support recovery rates at the higher throughput level but depending on performance, some of these initiatives may have the flexibility to be deferred until the Phase 3 expansion.

    To support the higher processing rates, Jacobina continues to increase underground mining capacity and has prepared an inventory of lower grade stopes and stockpiled ore on surface to provide supplementary mill feed during the ramp up phase. With the higher than planned processing rates that are now anticipated, the Company expects to continue drawing from this supplementary ore into the first half of 2022. New mobile mining equipment has been delivered to Jacobina with additional equipment planned to be received in the first quarter of 2022 to facilitate the increased mining capacity. A modest increase in underground development is also expected in 2022. The accelerated mine plan shows mill feed grades increasing over the next two years.

    The tailings storage strategy is aligned with the accelerated expansion timeline. Construction of the latest phase of the tailings storage facility was recently completed, providing tailings storage capacity at 8,500 tpd until the end of 2023. Further permitted phases of the tailings storage facility provide adequate storage capacity to support the life of mine plan. A comprehensive tailings storage strategy is well advanced to provide additional storage solutions including hydraulic backfill, paste fill, and a dry-stack tailings storage facility.

    The Company’s simplified approach for the Phase 2 expansion reduces capital expenditures, increases energy efficiency, and derisks the project. Capital costs for the Phase 2 expansion are estimated at approximately $20 million, with $15 million remaining to be spent in 2022.

    Lesen Sie auch

    The Phase 3 expansion to increase throughput to 10,000 tpd is being evaluated. Engineering is advancing in parallel with Phase 2, with a feasibility study for Phase 3 scheduled for completion in 2023.

    Seite 2 von 5



    Diskutieren Sie über die enthaltenen Werte



    globenewswire
    0 Follower
    Autor folgen

    Verfasst von globenewswire
    Yamana Gold Receives Permit at Jacobina, Initiating Ramp Up of Phase 2 Expansion, Expects Fourth Quarter Company Wide Production to Exceed 270,000 GEO With Costs Tracking to Be the Lowest of the Year - Seite 2 TORONTO, Dec. 06, 2021 (GLOBE NEWSWIRE) - YAMANA GOLD INC. (TSX:YRI; NYSE:AUY; LSE:AUY) (“Yamana” or “the Company”) is pleased to announce it has received the permit at its Jacobina mine to increase throughput to 10,000 tonnes per day (“tpd”). …

    Schreibe Deinen Kommentar

    Disclaimer