Ten Sixty Four ( Medusa Mining )--- Goldproduzent zu Niedrigkosten !!! (Seite 34)
eröffnet am 21.01.09 14:22:37 von
neuester Beitrag 03.04.24 19:39:59 von
neuester Beitrag 03.04.24 19:39:59 von
Beiträge: 763
ID: 1.147.714
ID: 1.147.714
Aufrufe heute: 3
Gesamt: 223.849
Gesamt: 223.849
Aktive User: 0
ISIN: AU0000221418 · WKN: A3DMQC · Symbol: X64
0,5650
AUD
-0,88 %
-0,0050 AUD
Letzter Kurs 27.02.23 Sydney
Werte aus der Branche Rohstoffe
Wertpapier | Kurs | Perf. % |
---|---|---|
0,8250 | +25,00 | |
0,8906 | +20,35 | |
5,6500 | +12,55 | |
0,6650 | +9,02 | |
1,2500 | +8,70 |
Wertpapier | Kurs | Perf. % |
---|---|---|
97,50 | -9,13 | |
1,0780 | -9,41 | |
12,460 | -16,06 | |
0,6600 | -24,57 | |
46,98 | -97,98 |
Beitrag zu dieser Diskussion schreiben
Daran sieht man das die Börse korrupt und manipulativ ist.
Antwort auf Beitrag Nr.: 48.221.125 von freddy1989 am 04.11.14 19:54:20bin nicht mehr aktuell da länger raus.
cashkosten zu 400 gab es nie.
war reine augenwischerei. bei AISC war es immer sehr eng mit der schwarzen 0.
der markt hats mittlerweile eh gefressen, deswegen der kurs.
cashkosten zu 400 gab es nie.
war reine augenwischerei. bei AISC war es immer sehr eng mit der schwarzen 0.
der markt hats mittlerweile eh gefressen, deswegen der kurs.
Hey mal nee Frage hab irgendwas verpasst ich bin davon ausgegangen das die Cash kosten um die 400 Dollar liegen weil es ja auch so in der Vergangenheit war.
Forecasted AISC: US$900 to US$1,000 per ounce
Wie kommt es zu diesem Cash kosten anstieg?? oder sind das die zukünftigen Cash kosten?
Forecasted AISC: US$900 to US$1,000 per ounce
Wie kommt es zu diesem Cash kosten anstieg?? oder sind das die zukünftigen Cash kosten?
Forecasted AISC: US$900 to US$1,000 per ounceForecasted AISC: US$900 to US$1,000 per ounce
also 1000 dollar wären im vgl zur vergangenheit schon eine hausnummer für medusa.
also 1000 dollar wären im vgl zur vergangenheit schon eine hausnummer für medusa.
ANNOUNCEMENT
3 November 2014
INVESTOR PRESENTATION
FISCAL YEAR 2014/15 GUIDANCE
-Forecasted gold production: 95,000 to 100,000 ounces
-Average head grade of > 5 g/t
-Mill recovery > 92%
-Forecasted cash costs: US$400 to US$450 per ounce
-Forecasted AISC: US$900 to US$1,000 per ounce
-Immediate focus:
improving efficiencies and reducing costs
Co-O MILL
-New SAG mill operating satisfactorily
-Recovery Q1-2014 at 92%
-All tailings detoxified
-Grid hydro power at mine and mill (standby diesel power at Mine and Mill)
-Grind size optimisation progressing towards 80% passing 75 microns (currently 75%)
-Two new tanks to increase leach time and flexibility due on line in early 2015
-Old 1,000 tpd mill on standby
Co-O MINE
-25 year Mining Licence (renewable by another 25 years)
-8 levels at 50 metre spacing
~ 60 priority headings
~ 100 stopes
>=1,500 metres development per month (5,037 metres for Q1)
-Winze from Level 9 to Level 10 underway
-L8 Shaft upgrade to increase combined mine haulage to 60,000 tonnes per month
-Level 8 now developed sufficiently for sustainable production
-Planned E15 Shaft to Level 8, then Level 12, then Level 16.
Estimated cost US$12M over 27-30 months to Level 8
Quelle: http://www.medusamining.com.au/
Investor Presentation November 2014
Ist hier noch jemand dabei?
3 November 2014
INVESTOR PRESENTATION
FISCAL YEAR 2014/15 GUIDANCE
-Forecasted gold production: 95,000 to 100,000 ounces
-Average head grade of > 5 g/t
-Mill recovery > 92%
-Forecasted cash costs: US$400 to US$450 per ounce
-Forecasted AISC: US$900 to US$1,000 per ounce
-Immediate focus:
improving efficiencies and reducing costs
Co-O MILL
-New SAG mill operating satisfactorily
-Recovery Q1-2014 at 92%
-All tailings detoxified
-Grid hydro power at mine and mill (standby diesel power at Mine and Mill)
-Grind size optimisation progressing towards 80% passing 75 microns (currently 75%)
-Two new tanks to increase leach time and flexibility due on line in early 2015
-Old 1,000 tpd mill on standby
Co-O MINE
-25 year Mining Licence (renewable by another 25 years)
-8 levels at 50 metre spacing
~ 60 priority headings
~ 100 stopes
>=1,500 metres development per month (5,037 metres for Q1)
-Winze from Level 9 to Level 10 underway
-L8 Shaft upgrade to increase combined mine haulage to 60,000 tonnes per month
-Level 8 now developed sufficiently for sustainable production
-Planned E15 Shaft to Level 8, then Level 12, then Level 16.
Estimated cost US$12M over 27-30 months to Level 8
Quelle: http://www.medusamining.com.au/
Investor Presentation November 2014
Ist hier noch jemand dabei?
Da hab ich mich ja sauber getäuscht - mann.
Mein Ausritt ins Gold- und Silberlager ist ein teurer Spass.
Interessant heute auf Tradegate:
Wenn ich eine Kauforder reinsetze, heute z.B. 3.000 Stück zu 0,371,
setzt sich sofort eine Order +0,001 drüber hier also 0,372.
Mein Ausritt ins Gold- und Silberlager ist ein teurer Spass.
Interessant heute auf Tradegate:
Wenn ich eine Kauforder reinsetze, heute z.B. 3.000 Stück zu 0,371,
setzt sich sofort eine Order +0,001 drüber hier also 0,372.
vielleicht hast du da das ATL erwischt.
Am Vortag gab's ja eine Unfall.
ANNOUNCEMENT
17 October 2014
Co-O MINE UNDERGROUND ACCIDENT
Heute kamen Quartalszahlen:
QUARTERLY ACTIVITIES REPORT
PERIOD ENDED
30 SEPTEMBER 2014
Co-O MINE PRODUCTION
Production: 21,018 ounces at a head grade 5.02 g/t gold and cash costs of US$382 per ounce (June 2014 quarter of 17,615 ounces at a head grade of 4.99 g/t gold and cash costs of US$431 per ounce).
-Production guidance: to 31 December 2014, 40,000 to 45,000 ounces. A new full year guidance will be provided on completion of a mine review.
-Mill performance: gold recovery averaged 92% (June 2014 quarter 85%). Grind size improved to 75% passing 75 microns.
-Development: Development averaged 1,679 metres per month.
-Shaft haulage: L8 Shaft upgrade is planned for 21 December 2014 to 13 January 2015 to increase the combined mine haulage capacity to approximately 60,000 tonnes per month.
-Mine review: Strategic operations review which commenced in early September to optimise long term mine planning, is nearing completion.
Co-O MINE RESOURCES AND RESERVES
-Total Indicated and Inferred Mineral Resources are estimated at 4.34 million tonnes at a grade of 10.1 g/t gold containing 1.41 million ounces of gold.
-Probable Ore Reserves are estimated at 1.92 million tonnes at a grade of 7.22 g/t gold containing 0.45 million ounces of gold.
Co-O MINE EXPLORATION
-Underground drilling results include 1.15 metres at 15.21 g/t Au, 1.40 metres at 24.38g/t Au, 3.95 metres at 4.59 g/t Au and 2.60 metres at 14.44 g/t Au.
-Surface exploration focusing on the North Tinago vein set adjacent to the north side of the mine. Geophysics survey completed.
TAMBIS AREA
-Drilling completed at B2 Discovery area, with last best result of 11.85m at 9.8 g/t Au from 280.6m depth in hole TDH345.
-Downhole geophysics survey in B2 Discovery area planned in the December quarter subject to contractor availability.
-Re-working of the Bananghilig Deposit interpretations underway. Additional metallurgical test work is planned.
CORPORATE & FINANCIALS (unaudited)
-Total cash and cash equivalent in gold on metal account at the end of quarter of approximately US$15.50 million.
-Mr Geoff Davis was appointed interim Chief Executive Officer on 01 September 2014,
Mal sehen, ob das der Boden war?
Am Vortag gab's ja eine Unfall.
ANNOUNCEMENT
17 October 2014
Co-O MINE UNDERGROUND ACCIDENT
Heute kamen Quartalszahlen:
QUARTERLY ACTIVITIES REPORT
PERIOD ENDED
30 SEPTEMBER 2014
Co-O MINE PRODUCTION
Production: 21,018 ounces at a head grade 5.02 g/t gold and cash costs of US$382 per ounce (June 2014 quarter of 17,615 ounces at a head grade of 4.99 g/t gold and cash costs of US$431 per ounce).
-Production guidance: to 31 December 2014, 40,000 to 45,000 ounces. A new full year guidance will be provided on completion of a mine review.
-Mill performance: gold recovery averaged 92% (June 2014 quarter 85%). Grind size improved to 75% passing 75 microns.
-Development: Development averaged 1,679 metres per month.
-Shaft haulage: L8 Shaft upgrade is planned for 21 December 2014 to 13 January 2015 to increase the combined mine haulage capacity to approximately 60,000 tonnes per month.
-Mine review: Strategic operations review which commenced in early September to optimise long term mine planning, is nearing completion.
Co-O MINE RESOURCES AND RESERVES
-Total Indicated and Inferred Mineral Resources are estimated at 4.34 million tonnes at a grade of 10.1 g/t gold containing 1.41 million ounces of gold.
-Probable Ore Reserves are estimated at 1.92 million tonnes at a grade of 7.22 g/t gold containing 0.45 million ounces of gold.
Co-O MINE EXPLORATION
-Underground drilling results include 1.15 metres at 15.21 g/t Au, 1.40 metres at 24.38g/t Au, 3.95 metres at 4.59 g/t Au and 2.60 metres at 14.44 g/t Au.
-Surface exploration focusing on the North Tinago vein set adjacent to the north side of the mine. Geophysics survey completed.
TAMBIS AREA
-Drilling completed at B2 Discovery area, with last best result of 11.85m at 9.8 g/t Au from 280.6m depth in hole TDH345.
-Downhole geophysics survey in B2 Discovery area planned in the December quarter subject to contractor availability.
-Re-working of the Bananghilig Deposit interpretations underway. Additional metallurgical test work is planned.
CORPORATE & FINANCIALS (unaudited)
-Total cash and cash equivalent in gold on metal account at the end of quarter of approximately US$15.50 million.
-Mr Geoff Davis was appointed interim Chief Executive Officer on 01 September 2014,
Mal sehen, ob das der Boden war?
Antwort auf Beitrag Nr.: 48.014.785 von phranque am 12.10.14 21:43:39
einstig war wol etwas früh
bin heute morgen mit 25%verlußt ausgestoppt worden
Werden die revidierten Reserven und Ressourcenschätzungen Abschreibungen nach sich ziehen?
Kann ja eigentlich nicht sein, sonst müsste der jetzige Buchwert ja gigantisch sein. Vielleicht hat da aber ein anderer Boardteilnehmer bessere Kenntnisse?!
Ich lag hier bzgl. der Kursentwicklung meistens falsch - hätte nie gedacht auf dieses Niveau zu krachen. Was mich wundert ist, dass der Goldpreis angesichts der aufkommenden Ängste nicht längst >1500 USD steht!
Kann ja eigentlich nicht sein, sonst müsste der jetzige Buchwert ja gigantisch sein. Vielleicht hat da aber ein anderer Boardteilnehmer bessere Kenntnisse?!
Ich lag hier bzgl. der Kursentwicklung meistens falsch - hätte nie gedacht auf dieses Niveau zu krachen. Was mich wundert ist, dass der Goldpreis angesichts der aufkommenden Ängste nicht längst >1500 USD steht!
Werden die revidierten Reserven und Ressourcenschätzungen Abschreibungen nach sich ziehen?