checkAd

    Anlagen- und Maschinenbau für Minenbetreiber etc. (Seite 8)

    eröffnet am 08.02.17 20:51:00 von
    neuester Beitrag 18.04.24 11:14:43 von
    Beiträge: 117
    ID: 1.246.436
    Aufrufe heute: 1
    Gesamt: 8.811
    Aktive User: 0

    ISIN: FI0009014575 · WKN: A0LBTW · Symbol: M6Q
    11,335
     
    EUR
    +0,67 %
    +0,075 EUR
    Letzter Kurs 14:30:28 Tradegate

    Werte aus der Branche Maschinenbau

    WertpapierKursPerf. %
    21,370+36,99
    42,00+26,58
    27,93+24,47
    0,8236+21,40
    8,7600+21,16

    Beitrag zu dieser Diskussion schreiben

     Durchsuchen
    • 1
    • 8
    • 12

    Begriffe und/oder Benutzer

     

    Top-Postings

     Ja Nein
      Avatar
      schrieb am 26.10.18 19:02:49
      Beitrag Nr. 47 ()
      Antwort auf Beitrag Nr.: 59.064.655 von faultcode am 26.10.18 13:01:28Cristal Global aus Saudi-Arabien war's:

      https://www.reuters.com/article/outotec-results-project/upda…

      =>
      ...
      It did not name the project but in effect indicated that it concerned a furnace ordered by chemicals company Cristal Global in Saudi Arabia. Outotec has previously said that the value of the turnkey deal of the smelter with two furnaces was 350 million euros ($398 million).

      “Both furnaces had their challenges during the original start-ups in 2015 and 2016. Furnace 1 was repaired and rebuilt, but during the ongoing start-up of the repaired furnace, there were problems and the start-up operation was terminated,” Outotec said in a statement.

      Cristal was not immediately available for a comment.

      ...
      3 Antworten
      Avatar
      schrieb am 26.10.18 13:01:28
      Beitrag Nr. 46 ()
      Antwort auf Beitrag Nr.: 58.992.357 von faultcode am 18.10.18 14:00:51
      -27% -- Outotec warns about possible material additional costs related to a large project
      zu früh!

      =>

      OUTOTEC OYJ STOCK EXCHANGE RELEASE OCTOBER 26, 2018 at 9:00 AM

      Outotec warns about possible material additional costs related to a large project

      Outotec has delivered a first-of-its-kind ilmenite smelter, with two large alternating current (AC) electric furnaces, as part of a greenfield plant delivery signed in 2012. Both furnaces had their challenges during the original start-ups in 2015 and 2016. Furnace 1 was repaired and rebuilt, but during the ongoing start-up of the repaired furnace, there were problems and the start-up operation was terminated. Investigation of the furnace will be made when the furnace has cooled down, which takes approximately one month.

      Currently it is estimated that potentially rebuilding a new furnace will take approximately one year. At this point, the cause of the problem with the start-up is not clear. In addition, it is too early to assess the total financial impact of any repairs that may be required. If it transpires that responsibility for this incident rests with Outotec, then the cost for Outotec will be material. In that case, it would have a material impact to Outotec's 2018 adjusted EBIT.

      Outotec announces additional information when available.

      Outotec will announce its Q3/2018 interim report on October 31, 2018.
      4 Antworten
      Avatar
      schrieb am 18.10.18 14:00:51
      Beitrag Nr. 45 ()
      Antwort auf Beitrag Nr.: 58.297.481 von faultcode am 25.07.18 12:23:52hier's ist einer überzeugt von Outotec:

      In accordance with the Securities Market Act, Chapter 9, Section 5, Catella Fondförvaltning AB, Sweden (556533-6210) has informed that its holdings in shares of Outotec Oyj (OTE1V) on October 16, 2018 has exceeded 5%, and is 5.008% with 9,171,005 shares.


      https://www.wallstreet-online.de/nachricht/10939242-change-t…
      https://www.catella.com/en/sweden/catella-fonder
      5 Antworten
      Avatar
      schrieb am 25.07.18 12:23:52
      Beitrag Nr. 44 ()
      2018Q2



      => Kurs erholt sich wieder --> -1.3% NASDAQ OMX NORDIC
      6 Antworten
      Avatar
      schrieb am 17.07.18 23:35:42
      Beitrag Nr. 43 ()
      Antwort auf Beitrag Nr.: 58.207.670 von faultcode am 13.07.18 14:09:16Hi weiss jemand ob der BIOX Process der Firma wirklich so gut ist? ich habe gelesen das die Fosterville Mine in Australien angeblich US$743 und 95% Recovery hat...

      Was haltet ihr von dem BIOX Prozess als Lösung für das viele Sulfiderz in der Minen weltweit?

      Trading Spotlight

      Anzeige
      JanOne
      2,8200EUR -17,06 %
      Jetzt Countdown zum “Milliarden-Deal” gestartet!mehr zur Aktie »
      Avatar
      schrieb am 13.07.18 14:09:16
      Beitrag Nr. 42 ()
      Antwort auf Beitrag Nr.: 58.158.800 von faultcode am 06.07.18 23:50:48..und wieder einer:

      Outotec to deliver minerals processing technology to Russia
      https://globenewswire.com/news-release/2018/07/13/1537040/0/…
      =>
      Outotec has signed a contract for the delivery of minerals processing technology and equipment to a concentrator plant in Russia. The contract value booked in Outotec's 2018 second quarter order intake is approximately EUR 24 million. The equipment will be delivered as a natural part of the already started project.

      "We are happy to support our customer's target to improve the environmental performance of their operations. Outotec's dewatering, flotation, automation and analyzer solutions are designed for efficient and environmentally sound concentrate production. In addition, the included extensive advisory service package ensures fast ramp-up and performance of the concentrator plant", says Kimmo Kontola, head of Outotec's Minerals Processing business.
      1 Antwort
      Avatar
      schrieb am 06.07.18 23:50:48
      Beitrag Nr. 41 ()
      Antwort auf Beitrag Nr.: 58.144.559 von faultcode am 05.07.18 14:17:09und noch einer:

      Outotec to deliver a 35 MW biomass power plant to Turkey

      Outotec has signed a contract for the EPC delivery of a new 35 MW gross electrical biomass power plant to be built in Turkey. The order value is approximately EUR 55 million which has been booked in Outotec's 2018 second quarter order intake.

      Outotec is responsible for engineering, procurement and construction of the plant excluding the civil works. Based on Outotec's proprietary fluidized bed technology, the main process components in the delivery are the biomass storage system, fluidized bed boiler, turbine and the flue gas treatment system.

      The new plant designed by Outotec will be located close to the biomass sources in the agricultural area, where the disposal from large farms is becoming an environmental concern. The plant will generate green electricity to the national grid and produce clean fertilizer as a byproduct.

      Designed to operate below the strict European emission limits, the plant is expected to be fully operational in 2020.

      "This is a great achievement for Outotec and one of the first projects of the Turkish initiative for promoting green energy out of biomass.

      In 2016, we delivered and commissioned one of Turkey's first 30 MW power plants based on alternative fuel and are now happy to provide our fluidized bed technology for another green energy project," says Kalle Härkki, head of Outotec's Metals, Energy & Water business.
      2 Antworten
      Avatar
      schrieb am 05.07.18 14:17:09
      Beitrag Nr. 40 ()
      Antwort auf Beitrag Nr.: 58.100.677 von faultcode am 29.06.18 17:22:50
      Outotec to deliver minerals processing equipment to Kazakhstan
      https://globenewswire.com/news-release/2018/07/05/1533692/0/…

      Outotec has been awarded a contract for the delivery of flotation cells and automation for a base metal concentrator in Kazakhstan. The approximately EUR 15 million order has been booked in Outotec's 2018 second quarter order intake.

      "We are happy to support our customer in their efforts to improve their production processes and environmental performance. Outotec's energy-efficient flotation cells and advanced process automation solutions contribute to stable concentrate production and improved yield", says Kimmo Kontola, head of Minerals Processing business at Outotec.
      3 Antworten
      Avatar
      schrieb am 29.06.18 17:22:50
      Beitrag Nr. 39 ()
      Outotec to deliver technology for a tin smelter in Indonesia
      OUTOTEC OYJ PRESS RELEASE JUNE 29, 2018 AT 1:00 PM

      Outotec has agreed with the Indonesian PT TIMAH Tbk (TIMAH) for the design and delivery of Outotec Ausmelt® Top Submerged Lance (TSL) technology and equipment for a new tin smelter, to be located at the existing tin smelter site at Muntok, Indonesia. The order has been booked in Outotec's 2018 second quarter order intake. The contract value is not disclosed, but orders of this size and scope are typically valued at over EUR 10 million.

      Outotec and TIMAH entered into agreements for a technology license and process and basic engineering in 2017. Now, the scope of Outotec's delivery includes detailed engineering and supply of core proprietary equipment for the Ausmelt core technology package.

      TIMAH is Indonesia's largest integrated tin miner and tin processor, as well as one the world's largest refined tin exporter.

      Outotec's deliverables will take place over the next 2 years, and the TIMAH Ausmelt plant, to be designed to process tin concentrates for production of 45,000 tonnes of crude tin per annum, is expected to become operational in 2020.

      "We are pleased to cooperate with TIMAH and provide them with our proven, cost effective and environmentally friendly Outotec Ausmelt furnace process at their new smelter. The Ausmelt technology is widely used in tin production around the world," says Kalle Härkki, Head of Outotec's Metals, Energy & Water business.
      4 Antworten
      Avatar
      schrieb am 20.06.18 15:07:39
      Beitrag Nr. 38 ()
      Outotec to deliver technology for Boliden's sulfuric acid plant in Sweden
      OUTOTEC OYJ PRESS RELEASEE JUNE 20, 2018 AT 3:30 PM

      Outotec has agreed with the Sweden-based mining company Boliden on the design and delivery of an absorption section to be built for the sulfuric acid plant at the Rönnskär smelter. The order has been booked in Outotec's 2018 second quarter order intake. Typically orders of this size and scope are valued at over EUR 10 million.

      The Boliden Rönnskär plant is one of the world's most efficient copper smelters. The new absorption section designed by Outotec will be able to process the future gas volume from the upstream smelting process with high energy recovery...



      => Rönnskär plant:
      https://www.boliden.com/operations/smelters/boliden-ronnskar
      • 1
      • 8
      • 12
       DurchsuchenBeitrag schreiben


      Investoren beobachten auch:

      WertpapierPerf. %
      +3,89
      +0,10
      -0,31
      +5,43
      -0,35
      +6,64
      +1,43
      -1,25
      -0,83
      +2,05
      Anlagen- und Maschinenbau für Minenbetreiber etc.